Hi,
An oddity.
After you set the 18:00 hours, and before clicking OK, hit enter or tab.
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"Texasroy" <Texasroy@discussions.microsoft.com> wrote in message
news:7B73449A-0E41-483A-9D43-83801F2091B1@microsoft.com...
>I am trying to do what ifs on the working time needed to complete a number
>of
> tasks (which can all be done immediately - no dependencies). I have set
> the
> tasks as "Fixed Work" and the total work is 1720 hours. With one resource
> on
> a 5 day, 8 hour per day calendar with no holidays, I get the expected 215
> days duration when I level for the one resource (1720 divided by 8). I
> want
> to set the availability to be 10 hour days, then 12 hour days, then 8 hour
> with a 6 day work week, 10 hours with a 6 day work week and finally 12
> hours
> with a 6 day work week. When I go to set the 10 hours (change working
> time,
> Options, Default Start time I set to 7:00 am and end time to 6 pm and I
> also
> set the workweek default to match. However, I have noticed that when I go
> right back into the Change working time, the 7 am held, but the 6 pm
> doesn't,
> it has returned to 5 pm. When I level I get 192 working days (9 hours per
> day). What gives?