On Aug 1, 9:02*am, "Mike Glen" <glenATmvps.org> wrote:
> Yes, you can call the resource Workers, or Electricians or whatever and in
> the Resource Usage view, assign the Max Units to reflect your situation eg:
> 300% for 3 workers or whatever numbers you have. *Then assign that resource
> to the tasks and then level. *Project will then level assuming you haveno
> more than the Max Units you set. *However, you can't then assign one ofthem
> by name - it's one or the other.
>
> Hope this helps - please let us know how you get on 
>
> Mike Glen
> MS Project MVP
> Seehttp://tinyurl.com/2xbhcfor my free Project Tutorials
>
> =============
Hi, Mike,
I understand what you said. But if some people in the group take
vacation, how it would reflect to the Max units. Do I have to do it
manually? Is there a way I input the exceptional days for different
workers, and Max units for the group would be changed automatically?
Please help.
Thanks,
Tracey