Why won't Project Import/Export to/from Excel
Hello,
I have a group of Project users who need to import/export to/from Excel however, they all get "Operation Failed" errors. We think it may be because of patch KB948962. Does anyone know anything about this? TIA, Rich |
|
|||
|
Re: Why won't Project Import/Export to/from Excel
Hello Rich,
Have you tried changing the "Allow legacy file formats" on the security tab in Tools > Options. I don't recall if this was in the SP-3 push or the security fix you mention, but I believe project works with earlier versions of Excel than 2003 when exporting. I am using Project 2003 with SP-3 and when I turn off the option to allow loading, I get a message saying I have to enable it. I hope this helps. Let us know how you get along. Julie Project MVP Visit http://project.mvps.org/ for the FAQs and additional information about Microsoft Project "rich" <rich@discussions.microsoft.com> wrote in message news:1A504728-906F-4671-AD6F-3A516CC22053@microsoft.com... > Hello, > > I have a group of Project users who need to import/export to/from > Excel > however, they all get "Operation Failed" errors. We think it may be > because > of patch KB948962. Does anyone know anything about this? > > TIA, > > Rich |
|
|||
|
Re: Why won't Project Import/Export to/from Excel
Hi Julie -
I'm getting the exact same problem, just a dialogue box with 'Operation Failed' and nothing else. I've tried using an existing map and a new map but it's all the same. I don't appear to have the "Allow legacy file formats" option on the security tab in Tools > Options. Peace. ANTHONY "JulieS" wrote: > Hello Rich, > > Have you tried changing the "Allow legacy file formats" on the > security tab in Tools > Options. I don't recall if this was in the > SP-3 push or the security fix you mention, but I believe project works > with earlier versions of Excel than 2003 when exporting. I am using > Project 2003 with SP-3 and when I turn off the option to allow > loading, I get a message saying I have to enable it. > > I hope this helps. Let us know how you get along. > > Julie > Project MVP > > Visit http://project.mvps.org/ for the FAQs and additional information > about Microsoft Project > > "rich" <rich@discussions.microsoft.com> wrote in message > news:1A504728-906F-4671-AD6F-3A516CC22053@microsoft.com... > > Hello, > > > > I have a group of Project users who need to import/export to/from > > Excel > > however, they all get "Operation Failed" errors. We think it may be > > because > > of patch KB948962. Does anyone know anything about this? > > > > TIA, > > > > Rich > > > |
|
|||
|
Re: Why won't Project Import/Export to/from Excel
Hi Anthony,
Do you have SP-3 installed? Try installing that and enabling legacy formats and see if that helps. I hope this helps. Let us know how you get along. Julie Project MVP Visit http://project.mvps.org/ for the FAQs and additional information about Microsoft Project "carricka" <carricka@discussions.microsoft.com> wrote in message news:2156B51E-931D-42FC-819B-871D3459366E@microsoft.com... > Hi Julie - > > I'm getting the exact same problem, just a dialogue box with > 'Operation > Failed' and nothing else. I've tried using an existing map and a > new map but > it's all the same. > > I don't appear to have the "Allow legacy file formats" option on the > security tab in Tools > Options. > > Peace. > ANTHONY > > "JulieS" wrote: > >> Hello Rich, >> >> Have you tried changing the "Allow legacy file formats" on the >> security tab in Tools > Options. I don't recall if this was in the >> SP-3 push or the security fix you mention, but I believe project >> works >> with earlier versions of Excel than 2003 when exporting. I am >> using >> Project 2003 with SP-3 and when I turn off the option to allow >> loading, I get a message saying I have to enable it. >> >> I hope this helps. Let us know how you get along. >> >> Julie >> Project MVP >> >> Visit http://project.mvps.org/ for the FAQs and additional >> information >> about Microsoft Project >> >> "rich" <rich@discussions.microsoft.com> wrote in message >> news:1A504728-906F-4671-AD6F-3A516CC22053@microsoft.com... >> > Hello, >> > >> > I have a group of Project users who need to import/export to/from >> > Excel >> > however, they all get "Operation Failed" errors. We think it may >> > be >> > because >> > of patch KB948962. Does anyone know anything about this? >> > >> > TIA, >> > >> > Rich >> >> >> |
|
|||
|
Re: Why won't Project Import/Export to/from Excel
Hi Julie -
No, we're on SP2. I'll talk to the system administrator and will get back to you as and when it's installed. Thanks for the prompt reply - it's much appreciated. Peace, ANTHONY "JulieS" wrote: > Hi Anthony, > > Do you have SP-3 installed? Try installing that and enabling legacy > formats and see if that helps. > > I hope this helps. Let us know how you get along. > > Julie > Project MVP > > Visit http://project.mvps.org/ for the FAQs and additional information > about Microsoft Project > > > "carricka" <carricka@discussions.microsoft.com> wrote in message > news:2156B51E-931D-42FC-819B-871D3459366E@microsoft.com... > > Hi Julie - > > > > I'm getting the exact same problem, just a dialogue box with > > 'Operation > > Failed' and nothing else. I've tried using an existing map and a > > new map but > > it's all the same. > > > > I don't appear to have the "Allow legacy file formats" option on the > > security tab in Tools > Options. > > > > Peace. > > ANTHONY > > > > "JulieS" wrote: > > > >> Hello Rich, > >> > >> Have you tried changing the "Allow legacy file formats" on the > >> security tab in Tools > Options. I don't recall if this was in the > >> SP-3 push or the security fix you mention, but I believe project > >> works > >> with earlier versions of Excel than 2003 when exporting. I am > >> using > >> Project 2003 with SP-3 and when I turn off the option to allow > >> loading, I get a message saying I have to enable it. > >> > >> I hope this helps. Let us know how you get along. > >> > >> Julie > >> Project MVP > >> > >> Visit http://project.mvps.org/ for the FAQs and additional > >> information > >> about Microsoft Project > >> > >> "rich" <rich@discussions.microsoft.com> wrote in message > >> news:1A504728-906F-4671-AD6F-3A516CC22053@microsoft.com... > >> > Hello, > >> > > >> > I have a group of Project users who need to import/export to/from > >> > Excel > >> > however, they all get "Operation Failed" errors. We think it may > >> > be > >> > because > >> > of patch KB948962. Does anyone know anything about this? > >> > > >> > TIA, > >> > > >> > Rich > >> > >> > >> > > > |
|
|||
|
Re: Why won't Project Import/Export to/from Excel
You're welcome Anthony. Good luck.
Julie "carricka" <carricka@discussions.microsoft.com> wrote in message news:9D103683-F62D-4347-BAD0-AA96420AF200@microsoft.com... > Hi Julie - > > No, we're on SP2. I'll talk to the system administrator and will get > back to > you as and when it's installed. > > Thanks for the prompt reply - it's much appreciated. > > Peace, > > ANTHONY > > "JulieS" wrote: > >> Hi Anthony, >> >> Do you have SP-3 installed? Try installing that and enabling >> legacy >> formats and see if that helps. >> >> I hope this helps. Let us know how you get along. >> >> Julie >> Project MVP >> >> Visit http://project.mvps.org/ for the FAQs and additional >> information >> about Microsoft Project >> >> >> "carricka" <carricka@discussions.microsoft.com> wrote in message >> news:2156B51E-931D-42FC-819B-871D3459366E@microsoft.com... >> > Hi Julie - >> > >> > I'm getting the exact same problem, just a dialogue box with >> > 'Operation >> > Failed' and nothing else. I've tried using an existing map and a >> > new map but >> > it's all the same. >> > >> > I don't appear to have the "Allow legacy file formats" option on >> > the >> > security tab in Tools > Options. >> > >> > Peace. >> > ANTHONY >> > >> > "JulieS" wrote: >> > >> >> Hello Rich, >> >> >> >> Have you tried changing the "Allow legacy file formats" on the >> >> security tab in Tools > Options. I don't recall if this was in >> >> the >> >> SP-3 push or the security fix you mention, but I believe project >> >> works >> >> with earlier versions of Excel than 2003 when exporting. I am >> >> using >> >> Project 2003 with SP-3 and when I turn off the option to allow >> >> loading, I get a message saying I have to enable it. >> >> >> >> I hope this helps. Let us know how you get along. >> >> >> >> Julie >> >> Project MVP >> >> >> >> Visit http://project.mvps.org/ for the FAQs and additional >> >> information >> >> about Microsoft Project >> >> >> >> "rich" <rich@discussions.microsoft.com> wrote in message >> >> news:1A504728-906F-4671-AD6F-3A516CC22053@microsoft.com... >> >> > Hello, >> >> > >> >> > I have a group of Project users who need to import/export >> >> > to/from >> >> > Excel >> >> > however, they all get "Operation Failed" errors. We think it >> >> > may >> >> > be >> >> > because >> >> > of patch KB948962. Does anyone know anything about this? >> >> > >> >> > TIA, >> >> > >> >> > Rich >> >> >> >> >> >> >> >> >> |
|
|||
|
Re: Why won't Project Import/Export to/from Excel
Hi Julie -
SP3 installed on Project and all working fine. Thanks for your help!! ANTHONY "JulieS" wrote: > You're welcome Anthony. Good luck. > > Julie > > "carricka" <carricka@discussions.microsoft.com> wrote in message > news:9D103683-F62D-4347-BAD0-AA96420AF200@microsoft.com... > > Hi Julie - > > > > No, we're on SP2. I'll talk to the system administrator and will get > > back to > > you as and when it's installed. > > > > Thanks for the prompt reply - it's much appreciated. > > > > Peace, > > > > ANTHONY > > > > "JulieS" wrote: > > > >> Hi Anthony, > >> > >> Do you have SP-3 installed? Try installing that and enabling > >> legacy > >> formats and see if that helps. > >> > >> I hope this helps. Let us know how you get along. > >> > >> Julie > >> Project MVP > >> > >> Visit http://project.mvps.org/ for the FAQs and additional > >> information > >> about Microsoft Project > >> > >> > >> "carricka" <carricka@discussions.microsoft.com> wrote in message > >> news:2156B51E-931D-42FC-819B-871D3459366E@microsoft.com... > >> > Hi Julie - > >> > > >> > I'm getting the exact same problem, just a dialogue box with > >> > 'Operation > >> > Failed' and nothing else. I've tried using an existing map and a > >> > new map but > >> > it's all the same. > >> > > >> > I don't appear to have the "Allow legacy file formats" option on > >> > the > >> > security tab in Tools > Options. > >> > > >> > Peace. > >> > ANTHONY > >> > > >> > "JulieS" wrote: > >> > > >> >> Hello Rich, > >> >> > >> >> Have you tried changing the "Allow legacy file formats" on the > >> >> security tab in Tools > Options. I don't recall if this was in > >> >> the > >> >> SP-3 push or the security fix you mention, but I believe project > >> >> works > >> >> with earlier versions of Excel than 2003 when exporting. I am > >> >> using > >> >> Project 2003 with SP-3 and when I turn off the option to allow > >> >> loading, I get a message saying I have to enable it. > >> >> > >> >> I hope this helps. Let us know how you get along. > >> >> > >> >> Julie > >> >> Project MVP > >> >> > >> >> Visit http://project.mvps.org/ for the FAQs and additional > >> >> information > >> >> about Microsoft Project > >> >> > >> >> "rich" <rich@discussions.microsoft.com> wrote in message > >> >> news:1A504728-906F-4671-AD6F-3A516CC22053@microsoft.com... > >> >> > Hello, > >> >> > > >> >> > I have a group of Project users who need to import/export > >> >> > to/from > >> >> > Excel > >> >> > however, they all get "Operation Failed" errors. We think it > >> >> > may > >> >> > be > >> >> > because > >> >> > of patch KB948962. Does anyone know anything about this? > >> >> > > >> >> > TIA, > >> >> > > >> >> > Rich > >> >> > >> >> > >> >> > >> > >> > >> > > > |
|
|||
|
Re: Why won't Project Import/Export to/from Excel
Super Anthony. I'm glad all worked well. You're welcome for the
assist and thanks for the feedback. Julie "carricka" <carricka@discussions.microsoft.com> wrote in message news:C38FD68A-AC6A-45AF-9D66-E15BD9E5310C@microsoft.com... > Hi Julie - > > SP3 installed on Project and all working fine. Thanks for your > help!! > > ANTHONY > > "JulieS" wrote: > >> You're welcome Anthony. Good luck. >> >> Julie >> >> "carricka" <carricka@discussions.microsoft.com> wrote in message >> news:9D103683-F62D-4347-BAD0-AA96420AF200@microsoft.com... >> > Hi Julie - >> > >> > No, we're on SP2. I'll talk to the system administrator and will >> > get >> > back to >> > you as and when it's installed. >> > >> > Thanks for the prompt reply - it's much appreciated. >> > >> > Peace, >> > >> > ANTHONY >> > >> > "JulieS" wrote: >> > >> >> Hi Anthony, >> >> >> >> Do you have SP-3 installed? Try installing that and enabling >> >> legacy >> >> formats and see if that helps. >> >> >> >> I hope this helps. Let us know how you get along. >> >> >> >> Julie >> >> Project MVP >> >> >> >> Visit http://project.mvps.org/ for the FAQs and additional >> >> information >> >> about Microsoft Project >> >> >> >> >> >> "carricka" <carricka@discussions.microsoft.com> wrote in message >> >> news:2156B51E-931D-42FC-819B-871D3459366E@microsoft.com... >> >> > Hi Julie - >> >> > >> >> > I'm getting the exact same problem, just a dialogue box with >> >> > 'Operation >> >> > Failed' and nothing else. I've tried using an existing map >> >> > and a >> >> > new map but >> >> > it's all the same. >> >> > >> >> > I don't appear to have the "Allow legacy file formats" option >> >> > on >> >> > the >> >> > security tab in Tools > Options. >> >> > >> >> > Peace. >> >> > ANTHONY >> >> > >> >> > "JulieS" wrote: >> >> > >> >> >> Hello Rich, >> >> >> >> >> >> Have you tried changing the "Allow legacy file formats" on >> >> >> the >> >> >> security tab in Tools > Options. I don't recall if this was >> >> >> in >> >> >> the >> >> >> SP-3 push or the security fix you mention, but I believe >> >> >> project >> >> >> works >> >> >> with earlier versions of Excel than 2003 when exporting. I >> >> >> am >> >> >> using >> >> >> Project 2003 with SP-3 and when I turn off the option to >> >> >> allow >> >> >> loading, I get a message saying I have to enable it. >> >> >> >> >> >> I hope this helps. Let us know how you get along. >> >> >> >> >> >> Julie >> >> >> Project MVP >> >> >> >> >> >> Visit http://project.mvps.org/ for the FAQs and additional >> >> >> information >> >> >> about Microsoft Project >> >> >> >> >> >> "rich" <rich@discussions.microsoft.com> wrote in message >> >> >> news:1A504728-906F-4671-AD6F-3A516CC22053@microsoft.com... >> >> >> > Hello, >> >> >> > >> >> >> > I have a group of Project users who need to import/export >> >> >> > to/from >> >> >> > Excel >> >> >> > however, they all get "Operation Failed" errors. We think >> >> >> > it >> >> >> > may >> >> >> > be >> >> >> > because >> >> >> > of patch KB948962. Does anyone know anything about this? >> >> >> > >> >> >> > TIA, >> >> >> > >> >> >> > Rich >> >> >> >> >> >> >> >> >> >> >> >> >> >> >> >> >> >> |
![]() |
|