Change working time
I am trying to do what ifs on the working time needed to complete a number of
tasks (which can all be done immediately - no dependencies). I have set the tasks as "Fixed Work" and the total work is 1720 hours. With one resource on a 5 day, 8 hour per day calendar with no holidays, I get the expected 215 days duration when I level for the one resource (1720 divided by 8). I want to set the availability to be 10 hour days, then 12 hour days, then 8 hour with a 6 day work week, 10 hours with a 6 day work week and finally 12 hours with a 6 day work week. When I go to set the 10 hours (change working time, Options, Default Start time I set to 7:00 am and end time to 6 pm and I also set the workweek default to match. However, I have noticed that when I go right back into the Change working time, the 7 am held, but the 6 pm doesn't, it has returned to 5 pm. When I level I get 192 working days (9 hours per day). What gives? |
|
|||
|
Re: Change working time
Hi,
An oddity. After you set the 18:00 hours, and before clicking OK, hit enter or tab. -- Jan De Messemaeker Microsoft Project Most Valuable Professional +32 495 300 620 For availability check: http://users.online.be/prom-ade/Calendar.pdf "Texasroy" <Texasroy@discussions.microsoft.com> wrote in message news:7B73449A-0E41-483A-9D43-83801F2091B1@microsoft.com... >I am trying to do what ifs on the working time needed to complete a number >of > tasks (which can all be done immediately - no dependencies). I have set > the > tasks as "Fixed Work" and the total work is 1720 hours. With one resource > on > a 5 day, 8 hour per day calendar with no holidays, I get the expected 215 > days duration when I level for the one resource (1720 divided by 8). I > want > to set the availability to be 10 hour days, then 12 hour days, then 8 hour > with a 6 day work week, 10 hours with a 6 day work week and finally 12 > hours > with a 6 day work week. When I go to set the 10 hours (change working > time, > Options, Default Start time I set to 7:00 am and end time to 6 pm and I > also > set the workweek default to match. However, I have noticed that when I go > right back into the Change working time, the 7 am held, but the 6 pm > doesn't, > it has returned to 5 pm. When I level I get 192 working days (9 hours per > day). What gives? |
|
|||
|
Re: Change working time
Yep, that worked. I wondered when I would hit "OK" before, the box would not
close until I hit it a second time. When I do the "return" and then OK, the 6 pm time holds. Much thanks. "Jan De Messemaeker" wrote: > Hi, > > An oddity. > After you set the 18:00 hours, and before clicking OK, hit enter or tab. > > -- > Jan De Messemaeker > Microsoft Project Most Valuable Professional > +32 495 300 620 > For availability check: > http://users.online.be/prom-ade/Calendar.pdf > "Texasroy" <Texasroy@discussions.microsoft.com> wrote in message > news:7B73449A-0E41-483A-9D43-83801F2091B1@microsoft.com... > >I am trying to do what ifs on the working time needed to complete a number > >of > > tasks (which can all be done immediately - no dependencies). I have set > > the > > tasks as "Fixed Work" and the total work is 1720 hours. With one resource > > on > > a 5 day, 8 hour per day calendar with no holidays, I get the expected 215 > > days duration when I level for the one resource (1720 divided by 8). I > > want > > to set the availability to be 10 hour days, then 12 hour days, then 8 hour > > with a 6 day work week, 10 hours with a 6 day work week and finally 12 > > hours > > with a 6 day work week. When I go to set the 10 hours (change working > > time, > > Options, Default Start time I set to 7:00 am and end time to 6 pm and I > > also > > set the workweek default to match. However, I have noticed that when I go > > right back into the Change working time, the 7 am held, but the 6 pm > > doesn't, > > it has returned to 5 pm. When I level I get 192 working days (9 hours per > > day). What gives? > > > |
|
|||
|
Re: Change working time
You're welcome!
-- Jan De Messemaeker Microsoft Project Most Valuable Professional +32 495 300 620 For availability check: http://users.online.be/prom-ade/Calendar.pdf "Texasroy" <Texasroy@discussions.microsoft.com> wrote in message news:CB63A572-F9FF-4B1E-9308-EA259975F3A7@microsoft.com... > Yep, that worked. I wondered when I would hit "OK" before, the box would > not > close until I hit it a second time. When I do the "return" and then OK, > the > 6 pm time holds. Much thanks. > > "Jan De Messemaeker" wrote: > >> Hi, >> >> An oddity. >> After you set the 18:00 hours, and before clicking OK, hit enter or tab. >> >> -- >> Jan De Messemaeker >> Microsoft Project Most Valuable Professional >> +32 495 300 620 >> For availability check: >> http://users.online.be/prom-ade/Calendar.pdf >> "Texasroy" <Texasroy@discussions.microsoft.com> wrote in message >> news:7B73449A-0E41-483A-9D43-83801F2091B1@microsoft.com... >> >I am trying to do what ifs on the working time needed to complete a >> >number >> >of >> > tasks (which can all be done immediately - no dependencies). I have >> > set >> > the >> > tasks as "Fixed Work" and the total work is 1720 hours. With one >> > resource >> > on >> > a 5 day, 8 hour per day calendar with no holidays, I get the expected >> > 215 >> > days duration when I level for the one resource (1720 divided by 8). I >> > want >> > to set the availability to be 10 hour days, then 12 hour days, then 8 >> > hour >> > with a 6 day work week, 10 hours with a 6 day work week and finally 12 >> > hours >> > with a 6 day work week. When I go to set the 10 hours (change working >> > time, >> > Options, Default Start time I set to 7:00 am and end time to 6 pm and I >> > also >> > set the workweek default to match. However, I have noticed that when I >> > go >> > right back into the Change working time, the 7 am held, but the 6 pm >> > doesn't, >> > it has returned to 5 pm. When I level I get 192 working days (9 hours >> > per >> > day). What gives? >> >> >> |
|
|||
|
Re: Change working time
Setting the Tools, Options, Calendar, Default Start Time or Default End Time
fields DOES NOT change the workday times. To do that, you need to go to the Tools, ChangeWorkingTime menu and revise the calendars there. The options page fields you changed control the times that Project assumes should be added whenever you manually type a start or end date and do not include a specific time in your entry and that's all they do - they don't set working times in any way, shape, or manner. Similarly, changing the workweek hours on that page only changes the conversion factor used to convert a duration entry made in "weeks" into the actual duration unit Project always uses internally, namely minutes. Also, leveling a resource does not distribute their work over a task's duration - leveling operates when two or more tasks are scheduled for one resource at the same time resulting in his being booked to do more work in a period of time than he is able, effectively booked to be in two different places at the same time. Leveling will then delay one of those tasks so it doesn't start until after the resource is free'd up from the conflicting task. -- Steve House [Project MVP] MS Project Trainer & Consultant Visit http://project.mvps.org/faqs.htm for the FAQs "Texasroy" <Texasroy@discussions.microsoft.com> wrote in message news:7B73449A-0E41-483A-9D43-83801F2091B1@microsoft.com... >I am trying to do what ifs on the working time needed to complete a number >of > tasks (which can all be done immediately - no dependencies). I have set > the > tasks as "Fixed Work" and the total work is 1720 hours. With one resource > on > a 5 day, 8 hour per day calendar with no holidays, I get the expected 215 > days duration when I level for the one resource (1720 divided by 8). I > want > to set the availability to be 10 hour days, then 12 hour days, then 8 hour > with a 6 day work week, 10 hours with a 6 day work week and finally 12 > hours > with a 6 day work week. When I go to set the 10 hours (change working > time, > Options, Default Start time I set to 7:00 am and end time to 6 pm and I > also > set the workweek default to match. However, I have noticed that when I go > right back into the Change working time, the 7 am held, but the 6 pm > doesn't, > it has returned to 5 pm. When I level I get 192 working days (9 hours per > day). What gives? |
![]() |
|