impact of milestones on resource levelling / scheduling

What differences (other than the obvious display difference) are there
between the ordinary tasks and tasks flagged as milestones?

In particular, is there a difference in teh way project resource levelling
and schduling for them?
Reply With Quote
  #2 (permalink)  
Old 07-17-2008, 06:26 AM
Jan De Messemaeker
 
Posts: n/a
Re: impact of milestones on resource levelling / scheduling


Hi,

Simply put, no. They are handled as any other task.
But when they have a zero duration, hence no work, they won't be leveled of
course.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"JoGo" <JoGo@discussions.microsoft.com> wrote in message
news:31798729-9795-4628-98DC-CE26AC51EF9A@microsoft.com...
> What differences (other than the obvious display difference) are there
> between the ordinary tasks and tasks flagged as milestones?
>
> In particular, is there a difference in teh way project resource levelling
> and schduling for them?



Reply With Quote
  #3 (permalink)  
Old 07-20-2008, 01:44 PM
Steve House
 
Posts: n/a
Re: impact of milestones on resource levelling / scheduling

And adding to Jan's comment, since milestones have no duration and thus no
work, they shouldn't have resources assigned to them either, thus "leveling"
a milestone to resolve resource overallocations makes no sense. A
milestone's location in the schedule is solely and completely determined by
the scheduling of its predecessor tasks.

--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://project.mvps.org/faqs.htm for the FAQs



"JoGo" <JoGo@discussions.microsoft.com> wrote in message
news:31798729-9795-4628-98DC-CE26AC51EF9A@microsoft.com...
> What differences (other than the obvious display difference) are there
> between the ordinary tasks and tasks flagged as milestones?
>
> In particular, is there a difference in teh way project resource levelling
> and schduling for them?


Reply With Quote
Reply

  { mindfrost82.com } > Gadget Corner > Tech Newsgroups > Microsoft > MS Office > Project


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On



All times are GMT. The time now is 07:41 AM.


Powered by vBulletin, Copyright ©2000 - 2008, Jelsoft Enterprises Ltd.
Search Engine Friendly URLs by vBSEO 3.1.0 ©2007, Crawlability, Inc.
© 1999-2008 mindfrost82.com v11.0


Sponsors:
Cheap Loan | Loan | Home Loan | Mobile Phone | McDonalds



1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109