Go Back   { mindfrost82.com } > Gadget Corner > Tech Newsgroups > Microsoft > MS Office > Project

Reply
 
LinkBack Thread Tools Search this Thread Display Modes
  #1 (permalink)  
Old 07-17-2008, 07:25 AM
=?Utf-8?B?TkxD?=
 
Posts: n/a
Displaying actual working days on "Duration" column

Hi, I am trying to have the duration Column to calculate the actual number of
working days (not sure if it's the right term I'm using).

For example, I have a task summary named "Materials on Site", under this
task I have 2 indented tasks that each have duration of 1 day, 3 days apart
each other.

- Materials on Site
>task 1 (08/Jun/10 - 08/Jun/10) duration 1 day
>task 2 (08/Jun/14 - 08/Jun/14) duration 1 day


By default Project shows a duration of 5 days (10,11,12,13,14) for the task
summary, how do i set it to display the actual days required? (which is 2
days)

I hope this is clear, thanks a lot!
Reply With Quote
  #2 (permalink)  
Old 07-17-2008, 08:28 AM
Jan De Messemaeker
 
Posts: n/a
Re: Displaying actual working days on "Duration" column

Hi,

1. Insert a column Duration1
2. Tools, Customize, Fields, select Duration1
3. Click on the word Formula
4. In the formula window, click field, select duration
5. OK
6. In the customize fields window on the line "... for summary tasks..."
select Sum

That's it.

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"NLC" <NLC@discussions.microsoft.com> wrote in message
news:6035DFC4-9E23-4047-8AEF-D67C43898AF1@microsoft.com...
> Hi, I am trying to have the duration Column to calculate the actual number
> of
> working days (not sure if it's the right term I'm using).
>
> For example, I have a task summary named "Materials on Site", under this
> task I have 2 indented tasks that each have duration of 1 day, 3 days
> apart
> each other.
>
> - Materials on Site
>>task 1 (08/Jun/10 - 08/Jun/10) duration 1 day
>>task 2 (08/Jun/14 - 08/Jun/14) duration 1 day

>
> By default Project shows a duration of 5 days (10,11,12,13,14) for the
> task
> summary, how do i set it to display the actual days required? (which is 2
> days)
>
> I hope this is clear, thanks a lot!



Reply With Quote
  #3 (permalink)  
Old 07-17-2008, 01:22 PM
salgud
 
Posts: n/a
Re: Displaying actual working days on "Duration" column

On Thu, 17 Jul 2008 00:25:01 -0700, NLC wrote:

> Hi, I am trying to have the duration Column to calculate the actual number of
> working days (not sure if it's the right term I'm using).
>
> For example, I have a task summary named "Materials on Site", under this
> task I have 2 indented tasks that each have duration of 1 day, 3 days apart
> each other.
>
> - Materials on Site
>>task 1 (08/Jun/10 - 08/Jun/10) duration 1 day
>>task 2 (08/Jun/14 - 08/Jun/14) duration 1 day

>
> By default Project shows a duration of 5 days (10,11,12,13,14) for the task
> summary, how do i set it to display the actual days required? (which is 2
> days)
>
> I hope this is clear, thanks a lot!


Jan indicated how to get what you want. What you want is not called
"duration". It's called "work effort". All these things are defined in the
discipline of scheduling. You might want to do a little reading, it will
pay off, especially if you come to this, or other, forums looking for help.
Hope this helps in your world.
Reply With Quote
  #4 (permalink)  
Old 07-17-2008, 02:52 PM
John
 
Posts: n/a
Re: Displaying actual working days on "Duration" column

In article <6035DFC4-9E23-4047-8AEF-D67C43898AF1@microsoft.com>,
NLC <NLC@discussions.microsoft.com> wrote:

> Hi, I am trying to have the duration Column to calculate the actual number of
> working days (not sure if it's the right term I'm using).
>
> For example, I have a task summary named "Materials on Site", under this
> task I have 2 indented tasks that each have duration of 1 day, 3 days apart
> each other.
>
> - Materials on Site
> >task 1 (08/Jun/10 - 08/Jun/10) duration 1 day
> >task 2 (08/Jun/14 - 08/Jun/14) duration 1 day

>
> By default Project shows a duration of 5 days (10,11,12,13,14) for the task
> summary, how do i set it to display the actual days required? (which is 2
> days)
>
> I hope this is clear, thanks a lot!


NLC,
OK, let me throw my 2 cents into this one also. Jan provided an easy way
to get a summation of what you think you want. However, from your
description, (i.e. materials on site), what you want is not duration and
it is not work effort as Salgud indicated.

What you really appear to be tracking is the arrival of materials on
site. That is a milestone and it's duration should be "0'd, probably the
end of the day on June 10th and June 14th. Why in the world you want to
try and sum those up I have no idea - I guess we'd need to understand
the larger intent.

For milestones, duration at the summary level really has no meaning
other than the time span in working days between the milestones.

John
Project MVP
Reply With Quote
  #5 (permalink)  
Old 07-17-2008, 07:04 PM
salgud
 
Posts: n/a
Re: Displaying actual working days on "Duration" column

On Thu, 17 Jul 2008 07:52:32 -0700, John wrote:

> In article <6035DFC4-9E23-4047-8AEF-D67C43898AF1@microsoft.com>,
> NLC <NLC@discussions.microsoft.com> wrote:
>
>> Hi, I am trying to have the duration Column to calculate the actual number of
>> working days (not sure if it's the right term I'm using).
>>
>> For example, I have a task summary named "Materials on Site", under this
>> task I have 2 indented tasks that each have duration of 1 day, 3 days apart
>> each other.
>>
>> - Materials on Site
>>>task 1 (08/Jun/10 - 08/Jun/10) duration 1 day
>>>task 2 (08/Jun/14 - 08/Jun/14) duration 1 day

>>
>> By default Project shows a duration of 5 days (10,11,12,13,14) for the task
>> summary, how do i set it to display the actual days required? (which is 2
>> days)
>>
>> I hope this is clear, thanks a lot!

>
> NLC,
> OK, let me throw my 2 cents into this one also. Jan provided an easy way
> to get a summation of what you think you want. However, from your
> description, (i.e. materials on site), what you want is not duration and
> it is not work effort as Salgud indicated.
>
> What you really appear to be tracking is the arrival of materials on
> site. That is a milestone and it's duration should be "0'd, probably the
> end of the day on June 10th and June 14th. Why in the world you want to
> try and sum those up I have no idea - I guess we'd need to understand
> the larger intent.
>
> For milestones, duration at the summary level really has no meaning
> other than the time span in working days between the milestones.
>
> John
> Project MVP


In a case like this one, I consider it work effort. It's being done outside
the scheduling organization, so it's being tracked at a higher level than
at the resource level. In some cases, it could be considered a milestone
and tracked accordingly. However, tracking it as a milestone gives you no
control other than to reschedule it if necessary.
In others situations, it can be tracked as the OP is doing. He might want
to know if the first part of the effort is delayed so he can make
adjustments to the lag or the second part of the effort. In such a case,
the 1d and 2d durations can be considered work effort, since no tracking of
actual resources is occurring but they want to track whether it's all
happening on schedule. It's more flexible this way.
Reply With Quote
  #6 (permalink)  
Old 07-18-2008, 03:32 AM
John
 
Posts: n/a
Re: Displaying actual working days on "Duration" column

In article <u7cthlsm5ujo.dk615snvadfl$.dlg@40tude.net>,
salgud <spamboy6547@comcast.net> wrote:

> On Thu, 17 Jul 2008 07:52:32 -0700, John wrote:
>
> > In article <6035DFC4-9E23-4047-8AEF-D67C43898AF1@microsoft.com>,
> > NLC <NLC@discussions.microsoft.com> wrote:
> >
> >> Hi, I am trying to have the duration Column to calculate the actual number
> >> of
> >> working days (not sure if it's the right term I'm using).
> >>
> >> For example, I have a task summary named "Materials on Site", under this
> >> task I have 2 indented tasks that each have duration of 1 day, 3 days
> >> apart
> >> each other.
> >>
> >> - Materials on Site
> >>>task 1 (08/Jun/10 - 08/Jun/10) duration 1 day
> >>>task 2 (08/Jun/14 - 08/Jun/14) duration 1 day
> >>
> >> By default Project shows a duration of 5 days (10,11,12,13,14) for the
> >> task
> >> summary, how do i set it to display the actual days required? (which is 2
> >> days)
> >>
> >> I hope this is clear, thanks a lot!

> >
> > NLC,
> > OK, let me throw my 2 cents into this one also. Jan provided an easy way
> > to get a summation of what you think you want. However, from your
> > description, (i.e. materials on site), what you want is not duration and
> > it is not work effort as Salgud indicated.
> >
> > What you really appear to be tracking is the arrival of materials on
> > site. That is a milestone and it's duration should be "0'd, probably the
> > end of the day on June 10th and June 14th. Why in the world you want to
> > try and sum those up I have no idea - I guess we'd need to understand
> > the larger intent.
> >
> > For milestones, duration at the summary level really has no meaning
> > other than the time span in working days between the milestones.
> >
> > John
> > Project MVP

>
> In a case like this one, I consider it work effort. It's being done outside
> the scheduling organization, so it's being tracked at a higher level than
> at the resource level. In some cases, it could be considered a milestone
> and tracked accordingly. However, tracking it as a milestone gives you no
> control other than to reschedule it if necessary.
> In others situations, it can be tracked as the OP is doing. He might want
> to know if the first part of the effort is delayed so he can make
> adjustments to the lag or the second part of the effort. In such a case,
> the 1d and 2d durations can be considered work effort, since no tracking of
> actual resources is occurring but they want to track whether it's all
> happening on schedule. It's more flexible this way.


Salgud,
I'm not sure what you mean by work effort being, "... tracked at a
higher level than at the resource level", since that doesn't make too
much sense. Work effort with no resources to do it?

OK, let's assume for the moment that what the poster is really trying to
say is that he has two performance tasks that when completed, will
provide materials on site. If that is the case then indeed there is work
effort to provide those materials but the poster is confusing duration
with work. In Project duration and work are two completely different
concepts. Duration is the time span during which tasks are worked. Work
is the actual effort required by one or more resources to complete the
task. Given this assumption what the poster should be displaying is the
Work field. At the summary level that will sum up to the 2 day total -
assuming he has assigned one or more resources to perform 8 hours of
work on tasks 1 & 2.

John
Project MVP
Reply With Quote
  #7 (permalink)  
Old 07-18-2008, 02:19 PM
salgud
 
Posts: n/a
Re: Displaying actual working days on "Duration" column

On Thu, 17 Jul 2008 20:32:42 -0700, John wrote:

> In article <u7cthlsm5ujo.dk615snvadfl$.dlg@40tude.net>,
> salgud <spamboy6547@comcast.net> wrote:
>
>> On Thu, 17 Jul 2008 07:52:32 -0700, John wrote:
>>
>>> In article <6035DFC4-9E23-4047-8AEF-D67C43898AF1@microsoft.com>,
>>> NLC <NLC@discussions.microsoft.com> wrote:
>>>
>>>> Hi, I am trying to have the duration Column to calculate the actual number
>>>> of
>>>> working days (not sure if it's the right term I'm using).
>>>>
>>>> For example, I have a task summary named "Materials on Site", under this
>>>> task I have 2 indented tasks that each have duration of 1 day, 3 days
>>>> apart
>>>> each other.
>>>>
>>>> - Materials on Site
>>>>>task 1 (08/Jun/10 - 08/Jun/10) duration 1 day
>>>>>task 2 (08/Jun/14 - 08/Jun/14) duration 1 day
>>>>
>>>> By default Project shows a duration of 5 days (10,11,12,13,14) for the
>>>> task
>>>> summary, how do i set it to display the actual days required? (which is 2
>>>> days)
>>>>
>>>> I hope this is clear, thanks a lot!
>>>
>>> NLC,
>>> OK, let me throw my 2 cents into this one also. Jan provided an easy way
>>> to get a summation of what you think you want. However, from your
>>> description, (i.e. materials on site), what you want is not duration and
>>> it is not work effort as Salgud indicated.
>>>
>>> What you really appear to be tracking is the arrival of materials on
>>> site. That is a milestone and it's duration should be "0'd, probably the
>>> end of the day on June 10th and June 14th. Why in the world you want to
>>> try and sum those up I have no idea - I guess we'd need to understand
>>> the larger intent.
>>>
>>> For milestones, duration at the summary level really has no meaning
>>> other than the time span in working days between the milestones.
>>>
>>> John
>>> Project MVP

>>
>> In a case like this one, I consider it work effort. It's being done outside
>> the scheduling organization, so it's being tracked at a higher level than
>> at the resource level. In some cases, it could be considered a milestone
>> and tracked accordingly. However, tracking it as a milestone gives you no
>> control other than to reschedule it if necessary.
>> In others situations, it can be tracked as the OP is doing. He might want
>> to know if the first part of the effort is delayed so he can make
>> adjustments to the lag or the second part of the effort. In such a case,
>> the 1d and 2d durations can be considered work effort, since no tracking of
>> actual resources is occurring but they want to track whether it's all
>> happening on schedule. It's more flexible this way.

>
> Salgud,
> I'm not sure what you mean by work effort being, "... tracked at a
> higher level than at the resource level", since that doesn't make too
> much sense. Work effort with no resources to do it?
>
> OK, let's assume for the moment that what the poster is really trying to
> say is that he has two performance tasks that when completed, will
> provide materials on site. If that is the case then indeed there is work
> effort to provide those materials but the poster is confusing duration
> with work. In Project duration and work are two completely different
> concepts. Duration is the time span during which tasks are worked. Work
> is the actual effort required by one or more resources to complete the
> task. Given this assumption what the poster should be displaying is the
> Work field. At the summary level that will sum up to the 2 day total -
> assuming he has assigned one or more resources to perform 8 hours of
> work on tasks 1 & 2.
>
> John
> Project MVP


Thanks for the detailed explanation of duration and work. Who would have
thought?
Seriously, I think you just said in a very convoluted way, what I said
above. Hopefully, it helped the OP.
Reply With Quote
  #8 (permalink)  
Old 07-18-2008, 03:18 PM
John
 
Posts: n/a
Re: Displaying actual working days on "Duration" column

In article <1o3mmuzibstfj.15e5s3eygo5pe.dlg@40tude.net>,
salgud <spamboy6547@comcast.net> wrote:

> On Thu, 17 Jul 2008 20:32:42 -0700, John wrote:
>
> > In article <u7cthlsm5ujo.dk615snvadfl$.dlg@40tude.net>,
> > salgud <spamboy6547@comcast.net> wrote:
> >
> >> On Thu, 17 Jul 2008 07:52:32 -0700, John wrote:
> >>
> >>> In article <6035DFC4-9E23-4047-8AEF-D67C43898AF1@microsoft.com>,
> >>> NLC <NLC@discussions.microsoft.com> wrote:
> >>>
> >>>> Hi, I am trying to have the duration Column to calculate the actual
> >>>> number
> >>>> of
> >>>> working days (not sure if it's the right term I'm using).
> >>>>
> >>>> For example, I have a task summary named "Materials on Site", under this
> >>>> task I have 2 indented tasks that each have duration of 1 day, 3 days
> >>>> apart
> >>>> each other.
> >>>>
> >>>> - Materials on Site
> >>>>>task 1 (08/Jun/10 - 08/Jun/10) duration 1 day
> >>>>>task 2 (08/Jun/14 - 08/Jun/14) duration 1 day
> >>>>
> >>>> By default Project shows a duration of 5 days (10,11,12,13,14) for the
> >>>> task
> >>>> summary, how do i set it to display the actual days required? (which is
> >>>> 2
> >>>> days)
> >>>>
> >>>> I hope this is clear, thanks a lot!
> >>>
> >>> NLC,
> >>> OK, let me throw my 2 cents into this one also. Jan provided an easy way
> >>> to get a summation of what you think you want. However, from your
> >>> description, (i.e. materials on site), what you want is not duration and
> >>> it is not work effort as Salgud indicated.
> >>>
> >>> What you really appear to be tracking is the arrival of materials on
> >>> site. That is a milestone and it's duration should be "0'd, probably the
> >>> end of the day on June 10th and June 14th. Why in the world you want to
> >>> try and sum those up I have no idea - I guess we'd need to understand
> >>> the larger intent.
> >>>
> >>> For milestones, duration at the summary level really has no meaning
> >>> other than the time span in working days between the milestones.
> >>>
> >>> John
> >>> Project MVP
> >>
> >> In a case like this one, I consider it work effort. It's being done
> >> outside
> >> the scheduling organization, so it's being tracked at a higher level than
> >> at the resource level. In some cases, it could be considered a milestone
> >> and tracked accordingly. However, tracking it as a milestone gives you no
> >> control other than to reschedule it if necessary.
> >> In others situations, it can be tracked as the OP is doing. He might want
> >> to know if the first part of the effort is delayed so he can make
> >> adjustments to the lag or the second part of the effort. In such a case,
> >> the 1d and 2d durations can be considered work effort, since no tracking
> >> of
> >> actual resources is occurring but they want to track whether it's all
> >> happening on schedule. It's more flexible this way.

> >
> > Salgud,
> > I'm not sure what you mean by work effort being, "... tracked at a
> > higher level than at the resource level", since that doesn't make too
> > much sense. Work effort with no resources to do it?
> >
> > OK, let's assume for the moment that what the poster is really trying to
> > say is that he has two performance tasks that when completed, will
> > provide materials on site. If that is the case then indeed there is work
> > effort to provide those materials but the poster is confusing duration
> > with work. In Project duration and work are two completely different
> > concepts. Duration is the time span during which tasks are worked. Work
> > is the actual effort required by one or more resources to complete the
> > task. Given this assumption what the poster should be displaying is the
> > Work field. At the summary level that will sum up to the 2 day total -
> > assuming he has assigned one or more resources to perform 8 hours of
> > work on tasks 1 & 2.
> >
> > John
> > Project MVP

>
> Thanks for the detailed explanation of duration and work. Who would have
> thought?
> Seriously, I think you just said in a very convoluted way, what I said
> above. Hopefully, it helped the OP.


Salgud,
Confusing duration and work is a very common mistake for new users of
Project. Since they both relate to time, people naturally think they are
the same. Time and time again in this newsgroup we have explained the
difference and my guess is that we will have to keep explaining it.

And yes, I hope the original poster checks out the whole thread. His
post wasn't all that definitive. The tasks could either represent
completion milestones, as I assumed, or could in fact be a day of
effort, as you indicated. Either way, if I knew the larger context, I
could be of more help.

John
Project MVP
Reply With Quote
  #9 (permalink)  
Old 07-18-2008, 05:17 PM
Jan De Messemaeker
 
Posts: n/a
Re: Displaying actual working days on "Duration" column

Hi,

I'm probably a too simple person, but I think he just took my formula and
was happy :-)

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"John" <mjensen@theriver.com> wrote in message
news:mjensen-A1E16F.08183818072008@msnews.microsoft.com...
> In article <1o3mmuzibstfj.15e5s3eygo5pe.dlg@40tude.net>,
> salgud <spamboy6547@comcast.net> wrote:
>
>> On Thu, 17 Jul 2008 20:32:42 -0700, John wrote:
>>
>> > In article <u7cthlsm5ujo.dk615snvadfl$.dlg@40tude.net>,
>> > salgud <spamboy6547@comcast.net> wrote:
>> >
>> >> On Thu, 17 Jul 2008 07:52:32 -0700, John wrote:
>> >>
>> >>> In article <6035DFC4-9E23-4047-8AEF-D67C43898AF1@microsoft.com>,
>> >>> NLC <NLC@discussions.microsoft.com> wrote:
>> >>>
>> >>>> Hi, I am trying to have the duration Column to calculate the actual
>> >>>> number
>> >>>> of
>> >>>> working days (not sure if it's the right term I'm using).
>> >>>>
>> >>>> For example, I have a task summary named "Materials on Site", under
>> >>>> this
>> >>>> task I have 2 indented tasks that each have duration of 1 day, 3
>> >>>> days
>> >>>> apart
>> >>>> each other.
>> >>>>
>> >>>> - Materials on Site
>> >>>>>task 1 (08/Jun/10 - 08/Jun/10) duration 1 day
>> >>>>>task 2 (08/Jun/14 - 08/Jun/14) duration 1 day
>> >>>>
>> >>>> By default Project shows a duration of 5 days (10,11,12,13,14) for
>> >>>> the
>> >>>> task
>> >>>> summary, how do i set it to display the actual days required? (which
>> >>>> is
>> >>>> 2
>> >>>> days)
>> >>>>
>> >>>> I hope this is clear, thanks a lot!
>> >>>
>> >>> NLC,
>> >>> OK, let me throw my 2 cents into this one also. Jan provided an easy
>> >>> way
>> >>> to get a summation of what you think you want. However, from your
>> >>> description, (i.e. materials on site), what you want is not duration
>> >>> and
>> >>> it is not work effort as Salgud indicated.
>> >>>
>> >>> What you really appear to be tracking is the arrival of materials on
>> >>> site. That is a milestone and it's duration should be "0'd, probably
>> >>> the
>> >>> end of the day on June 10th and June 14th. Why in the world you want
>> >>> to
>> >>> try and sum those up I have no idea - I guess we'd need to understand
>> >>> the larger intent.
>> >>>
>> >>> For milestones, duration at the summary level really has no meaning
>> >>> other than the time span in working days between the milestones.
>> >>>
>> >>> John
>> >>> Project MVP
>> >>
>> >> In a case like this one, I consider it work effort. It's being done
>> >> outside
>> >> the scheduling organization, so it's being tracked at a higher level
>> >> than
>> >> at the resource level. In some cases, it could be considered a
>> >> milestone
>> >> and tracked accordingly. However, tracking it as a milestone gives you
>> >> no
>> >> control other than to reschedule it if necessary.
>> >> In others situations, it can be tracked as the OP is doing. He might
>> >> want
>> >> to know if the first part of the effort is delayed so he can make
>> >> adjustments to the lag or the second part of the effort. In such a
>> >> case,
>> >> the 1d and 2d durations can be considered work effort, since no
>> >> tracking
>> >> of
>> >> actual resources is occurring but they want to track whether it's all
>> >> happening on schedule. It's more flexible this way.
>> >
>> > Salgud,
>> > I'm not sure what you mean by work effort being, "... tracked at a
>> > higher level than at the resource level", since that doesn't make too
>> > much sense. Work effort with no resources to do it?
>> >
>> > OK, let's assume for the moment that what the poster is really trying
>> > to
>> > say is that he has two performance tasks that when completed, will
>> > provide materials on site. If that is the case then indeed there is
>> > work
>> > effort to provide those materials but the poster is confusing duration
>> > with work. In Project duration and work are two completely different
>> > concepts. Duration is the time span during which tasks are worked. Work
>> > is the actual effort required by one or more resources to complete the
>> > task. Given this assumption what the poster should be displaying is the
>> > Work field. At the summary level that will sum up to the 2 day total -
>> > assuming he has assigned one or more resources to perform 8 hours of
>> > work on tasks 1 & 2.
>> >
>> > John
>> > Project MVP

>>
>> Thanks for the detailed explanation of duration and work. Who would have
>> thought?
>> Seriously, I think you just said in a very convoluted way, what I said
>> above. Hopefully, it helped the OP.

>
> Salgud,
> Confusing duration and work is a very common mistake for new users of
> Project. Since they both relate to time, people naturally think they are
> the same. Time and time again in this newsgroup we have explained the
> difference and my guess is that we will have to keep explaining it.
>
> And yes, I hope the original poster checks out the whole thread. His
> post wasn't all that definitive. The tasks could either represent
> completion milestones, as I assumed, or could in fact be a day of
> effort, as you indicated. Either way, if I knew the larger context, I
> could be of more help.
>
> John
> Project MVP



Reply With Quote
Reply

  { mindfrost82.com } > Gadget Corner > Tech Newsgroups > Microsoft > MS Office > Project


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On



All times are GMT. The time now is 06:24 AM.


Powered by vBulletin, Copyright ©2000 - 2008, Jelsoft Enterprises Ltd.
Search Engine Friendly URLs by vBSEO 3.1.0 ©2007, Crawlability, Inc.
© 1999-2008 mindfrost82.com v11.0

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109