![]() |
|
|
|||||||
![]() |
|
|
LinkBack | Thread Tools | Search this Thread | Display Modes |
|
|||
|
Displaying actual working days on "Duration" column
Hi, I am trying to have the duration Column to calculate the actual number of
working days (not sure if it's the right term I'm using). For example, I have a task summary named "Materials on Site", under this task I have 2 indented tasks that each have duration of 1 day, 3 days apart each other. - Materials on Site >task 1 (08/Jun/10 - 08/Jun/10) duration 1 day >task 2 (08/Jun/14 - 08/Jun/14) duration 1 day By default Project shows a duration of 5 days (10,11,12,13,14) for the task summary, how do i set it to display the actual days required? (which is 2 days) I hope this is clear, thanks a lot! |
|
|||
|
Re: Displaying actual working days on "Duration" column
Hi,
1. Insert a column Duration1 2. Tools, Customize, Fields, select Duration1 3. Click on the word Formula 4. In the formula window, click field, select duration 5. OK 6. In the customize fields window on the line "... for summary tasks..." select Sum That's it. -- Jan De Messemaeker Microsoft Project Most Valuable Professional +32 495 300 620 For availability check: http://users.online.be/prom-ade/Calendar.pdf "NLC" <NLC@discussions.microsoft.com> wrote in message news:6035DFC4-9E23-4047-8AEF-D67C43898AF1@microsoft.com... > Hi, I am trying to have the duration Column to calculate the actual number > of > working days (not sure if it's the right term I'm using). > > For example, I have a task summary named "Materials on Site", under this > task I have 2 indented tasks that each have duration of 1 day, 3 days > apart > each other. > > - Materials on Site >>task 1 (08/Jun/10 - 08/Jun/10) duration 1 day >>task 2 (08/Jun/14 - 08/Jun/14) duration 1 day > > By default Project shows a duration of 5 days (10,11,12,13,14) for the > task > summary, how do i set it to display the actual days required? (which is 2 > days) > > I hope this is clear, thanks a lot! |
|
|||
|
Re: Displaying actual working days on "Duration" column
On Thu, 17 Jul 2008 00:25:01 -0700, NLC wrote:
> Hi, I am trying to have the duration Column to calculate the actual number of > working days (not sure if it's the right term I'm using). > > For example, I have a task summary named "Materials on Site", under this > task I have 2 indented tasks that each have duration of 1 day, 3 days apart > each other. > > - Materials on Site >>task 1 (08/Jun/10 - 08/Jun/10) duration 1 day >>task 2 (08/Jun/14 - 08/Jun/14) duration 1 day > > By default Project shows a duration of 5 days (10,11,12,13,14) for the task > summary, how do i set it to display the actual days required? (which is 2 > days) > > I hope this is clear, thanks a lot! Jan indicated how to get what you want. What you want is not called "duration". It's called "work effort". All these things are defined in the discipline of scheduling. You might want to do a little reading, it will pay off, especially if you come to this, or other, forums looking for help. Hope this helps in your world. |
|
|||
|
Re: Displaying actual working days on "Duration" column
In article <6035DFC4-9E23-4047-8AEF-D67C43898AF1@microsoft.com>,
NLC <NLC@discussions.microsoft.com> wrote: > Hi, I am trying to have the duration Column to calculate the actual number of > working days (not sure if it's the right term I'm using). > > For example, I have a task summary named "Materials on Site", under this > task I have 2 indented tasks that each have duration of 1 day, 3 days apart > each other. > > - Materials on Site > >task 1 (08/Jun/10 - 08/Jun/10) duration 1 day > >task 2 (08/Jun/14 - 08/Jun/14) duration 1 day > > By default Project shows a duration of 5 days (10,11,12,13,14) for the task > summary, how do i set it to display the actual days required? (which is 2 > days) > > I hope this is clear, thanks a lot! NLC, OK, let me throw my 2 cents into this one also. Jan provided an easy way to get a summation of what you think you want. However, from your description, (i.e. materials on site), what you want is not duration and it is not work effort as Salgud indicated. What you really appear to be tracking is the arrival of materials on site. That is a milestone and it's duration should be "0'd, probably the end of the day on June 10th and June 14th. Why in the world you want to try and sum those up I have no idea - I guess we'd need to understand the larger intent. For milestones, duration at the summary level really has no meaning other than the time span in working days between the milestones. John Project MVP |
|
|||
|
Re: Displaying actual working days on "Duration" column
On Thu, 17 Jul 2008 07:52:32 -0700, John wrote:
> In article <6035DFC4-9E23-4047-8AEF-D67C43898AF1@microsoft.com>, > NLC <NLC@discussions.microsoft.com> wrote: > >> Hi, I am trying to have the duration Column to calculate the actual number of >> working days (not sure if it's the right term I'm using). >> >> For example, I have a task summary named "Materials on Site", under this >> task I have 2 indented tasks that each have duration of 1 day, 3 days apart >> each other. >> >> - Materials on Site >>>task 1 (08/Jun/10 - 08/Jun/10) duration 1 day >>>task 2 (08/Jun/14 - 08/Jun/14) duration 1 day >> >> By default Project shows a duration of 5 days (10,11,12,13,14) for the task >> summary, how do i set it to display the actual days required? (which is 2 >> days) >> >> I hope this is clear, thanks a lot! > > NLC, > OK, let me throw my 2 cents into this one also. Jan provided an easy way > to get a summation of what you think you want. However, from your > description, (i.e. materials on site), what you want is not duration and > it is not work effort as Salgud indicated. > > What you really appear to be tracking is the arrival of materials on > site. That is a milestone and it's duration should be "0'd, probably the > end of the day on June 10th and June 14th. Why in the world you want to > try and sum those up I have no idea - I guess we'd need to understand > the larger intent. > > For milestones, duration at the summary level really has no meaning > other than the time span in working days between the milestones. > > John > Project MVP In a case like this one, I consider it work effort. It's being done outside the scheduling organization, so it's being tracked at a higher level than at the resource level. In some cases, it could be considered a milestone and tracked accordingly. However, tracking it as a milestone gives you no control other than to reschedule it if necessary. In others situations, it can be tracked as the OP is doing. He might want to know if the first part of the effort is delayed so he can make adjustments to the lag or the second part of the effort. In such a case, the 1d and 2d durations can be considered work effort, since no tracking of actual resources is occurring but they want to track whether it's all happening on schedule. It's more flexible this way. |
|
|||
|
Re: Displaying actual working days on "Duration" column
In article <u7cthlsm5ujo.dk615snvadfl$.dlg@40tude.net>,
salgud <spamboy6547@comcast.net> wrote: > On Thu, 17 Jul 2008 07:52:32 -0700, John wrote: > > > In article <6035DFC4-9E23-4047-8AEF-D67C43898AF1@microsoft.com>, > > NLC <NLC@discussions.microsoft.com> wrote: > > > >> Hi, I am trying to have the duration Column to calculate the actual number > >> of > >> working days (not sure if it's the right term I'm using). > >> > >> For example, I have a task summary named "Materials on Site", under this > >> task I have 2 indented tasks that each have duration of 1 day, 3 days > >> apart > >> each other. > >> > >> - Materials on Site > >>>task 1 (08/Jun/10 - 08/Jun/10) duration 1 day > >>>task 2 (08/Jun/14 - 08/Jun/14) duration 1 day > >> > >> By default Project shows a duration of 5 days (10,11,12,13,14) for the > >> task > >> summary, how do i set it to display the actual days required? (which is 2 > >> days) > >> > >> I hope this is clear, thanks a lot! > > > > NLC, > > OK, let me throw my 2 cents into this one also. Jan provided an easy way > > to get a summation of what you think you want. However, from your > > description, (i.e. materials on site), what you want is not duration and > > it is not work effort as Salgud indicated. > > > > What you really appear to be tracking is the arrival of materials on > > site. That is a milestone and it's duration should be "0'd, probably the > > end of the day on June 10th and June 14th. Why in the world you want to > > try and sum those up I have no idea - I guess we'd need to understand > > the larger intent. > > > > For milestones, duration at the summary level really has no meaning > > other than the time span in working days between the milestones. > > > > John > > Project MVP > > In a case like this one, I consider it work effort. It's being done outside > the scheduling organization, so it's being tracked at a higher level than > at the resource level. In some cases, it could be considered a milestone > and tracked accordingly. However, tracking it as a milestone gives you no > control other than to reschedule it if necessary. > In others situations, it can be tracked as the OP is doing. He might want > to know if the first part of the effort is delayed so he can make > adjustments to the lag or the second part of the effort. In such a case, > the 1d and 2d durations can be considered work effort, since no tracking of > actual resources is occurring but they want to track whether it's all > happening on schedule. It's more flexible this way. Salgud, I'm not sure what you mean by work effort being, "... tracked at a higher level than at the resource level", since that doesn't make too much sense. Work effort with no resources to do it? OK, let's assume for the moment that what the poster is really trying to say is that he has two performance tasks that when completed, will provide materials on site. If that is the case then indeed there is work effort to provide those materials but the poster is confusing duration with work. In Project duration and work are two completely different concepts. Duration is the time span during which tasks are worked. Work is the actual effort required by one or more resources to complete the task. Given this assumption what the poster should be displaying is the Work field. At the summary level that will sum up to the 2 day total - assuming he has assigned one or more resources to perform 8 hours of work on tasks 1 & 2. John Project MVP |
|
|||
|
Re: Displaying actual working days on "Duration" column
On Thu, 17 Jul 2008 20:32:42 -0700, John wrote:
> In article <u7cthlsm5ujo.dk615snvadfl$.dlg@40tude.net>, > salgud <spamboy6547@comcast.net> wrote: > >> On Thu, 17 Jul 2008 07:52:32 -0700, John wrote: >> >>> In article <6035DFC4-9E23-4047-8AEF-D67C43898AF1@microsoft.com>, >>> NLC <NLC@discussions.microsoft.com> wrote: >>> >>>> Hi, I am trying to have the duration Column to calculate the actual number >>>> of >>>> working days (not sure if it's the right term I'm using). >>>> >>>> For example, I have a task summary named "Materials on Site", under this >>>> task I have 2 indented tasks that each have duration of 1 day, 3 days >>>> apart >>>> each other. >>>> >>>> - Materials on Site >>>>>task 1 (08/Jun/10 - 08/Jun/10) duration 1 day >>>>>task 2 (08/Jun/14 - 08/Jun/14) duration 1 day >>>> >>>> By default Project shows a duration of 5 days (10,11,12,13,14) for the >>>> task >>>> summary, how do i set it to display the actual days required? (which is 2 >>>> days) >>>> >>>> I hope this is clear, thanks a lot! >>> >>> NLC, >>> OK, let me throw my 2 cents into this one also. Jan provided an easy way >>> to get a summation of what you think you want. However, from your >>> description, (i.e. materials on site), what you want is not duration and >>> it is not work effort as Salgud indicated. >>> >>> What you really appear to be tracking is the arrival of materials on >>> site. That is a milestone and it's duration should be "0'd, probably the >>> end of the day on June 10th and June 14th. Why in the world you want to >>> try and sum those up I have no idea - I guess we'd need to understand >>> the larger intent. >>> >>> For milestones, duration at the summary level really has no meaning >>> other than the time span in working days between the milestones. >>> >>> John >>> Project MVP >> >> In a case like this one, I consider it work effort. It's being done outside >> the scheduling organization, so it's being tracked at a higher level than >> at the resource level. In some cases, it could be considered a milestone >> and tracked accordingly. However, tracking it as a milestone gives you no >> control other than to reschedule it if necessary. >> In others situations, it can be tracked as the OP is doing. He might want >> to know if the first part of the effort is delayed so he can make >> adjustments to the lag or the second part of the effort. In such a case, >> the 1d and 2d durations can be considered work effort, since no tracking of >> actual resources is occurring but they want to track whether it's all >> happening on schedule. It's more flexible this way. > > Salgud, > I'm not sure what you mean by work effort being, "... tracked at a > higher level than at the resource level", since that doesn't make too > much sense. Work effort with no resources to do it? > > OK, let's assume for the moment that what the poster is really trying to > say is that he has two performance tasks that when completed, will > provide materials on site. If that is the case then indeed there is work > effort to provide those materials but the poster is confusing duration > with work. In Project duration and work are two completely different > concepts. Duration is the time span during which tasks are worked. Work > is the actual effort required by one or more resources to complete the > task. Given this assumption what the poster should be displaying is the > Work field. At the summary level that will sum up to the 2 day total - > assuming he has assigned one or more resources to perform 8 hours of > work on tasks 1 & 2. > > John > Project MVP Thanks for the detailed explanation of duration and work. Who would have thought? Seriously, I think you just said in a very convoluted way, what I said above. Hopefully, it helped the OP. |
|
|||
|
Re: Displaying actual working days on "Duration" column
In article <1o3mmuzibstfj.15e5s3eygo5pe.dlg@40tude.net>,
salgud <spamboy6547@comcast.net> wrote: > On Thu, 17 Jul 2008 20:32:42 -0700, John wrote: > > > In article <u7cthlsm5ujo.dk615snvadfl$.dlg@40tude.net>, > > salgud <spamboy6547@comcast.net> wrote: > > > >> On Thu, 17 Jul 2008 07:52:32 -0700, John wrote: > >> > >>> In article <6035DFC4-9E23-4047-8AEF-D67C43898AF1@microsoft.com>, > >>> NLC <NLC@discussions.microsoft.com> wrote: > >>> > >>>> Hi, I am trying to have the duration Column to calculate the actual > >>>> number > >>>> of > >>>> working days (not sure if it's the right term I'm using). > >>>> > >>>> For example, I have a task summary named "Materials on Site", under this > >>>> task I have 2 indented tasks that each have duration of 1 day, 3 days > >>>> apart > >>>> each other. > >>>> > >>>> - Materials on Site > >>>>>task 1 (08/Jun/10 - 08/Jun/10) duration 1 day > >>>>>task 2 (08/Jun/14 - 08/Jun/14) duration 1 day > >>>> > >>>> By default Project shows a duration of 5 days (10,11,12,13,14) for the > >>>> task > >>>> summary, how do i set it to display the actual days required? (which is > >>>> 2 > >>>> days) > >>>> > >>>> I hope this is clear, thanks a lot! > >>> > >>> NLC, > >>> OK, let me throw my 2 cents into this one also. Jan provided an easy way > >>> to get a summation of what you think you want. However, from your > >>> description, (i.e. materials on site), what you want is not duration and > >>> it is not work effort as Salgud indicated. > >>> > >>> What you really appear to be tracking is the arrival of materials on > >>> site. That is a milestone and it's duration should be "0'd, probably the > >>> end of the day on June 10th and June 14th. Why in the world you want to > >>> try and sum those up I have no idea - I guess we'd need to understand > >>> the larger intent. > >>> > >>> For milestones, duration at the summary level really has no meaning > >>> other than the time span in working days between the milestones. > >>> > >>> John > >>> Project MVP > >> > >> In a case like this one, I consider it work effort. It's being done > >> outside > >> the scheduling organization, so it's being tracked at a higher level than > >> at the resource level. In some cases, it could be considered a milestone > >> and tracked accordingly. However, tracking it as a milestone gives you no > >> control other than to reschedule it if necessary. > >> In others situations, it can be tracked as the OP is doing. He might want > >> to know if the first part of the effort is delayed so he can make > >> adjustments to the lag or the second part of the effort. In such a case, > >> the 1d and 2d durations can be considered work effort, since no tracking > >> of > >> actual resources is occurring but they want to track whether it's all > >> happening on schedule. It's more flexible this way. > > > > Salgud, > > I'm not sure what you mean by work effort being, "... tracked at a > > higher level than at the resource level", since that doesn't make too > > much sense. Work effort with no resources to do it? > > > > OK, let's assume for the moment that what the poster is really trying to > > say is that he has two performance tasks that when completed, will > > provide materials on site. If that is the case then indeed there is work > > effort to provide those materials but the poster is confusing duration > > with work. In Project duration and work are two completely different > > concepts. Duration is the time span during which tasks are worked. Work > > is the actual effort required by one or more resources to complete the > > task. Given this assumption what the poster should be displaying is the > > Work field. At the summary level that will sum up to the 2 day total - > > assuming he has assigned one or more resources to perform 8 hours of > > work on tasks 1 & 2. > > > > John > > Project MVP > > Thanks for the detailed explanation of duration and work. Who would have > thought? > Seriously, I think you just said in a very convoluted way, what I said > above. Hopefully, it helped the OP. Salgud, Confusing duration and work is a very common mistake for new users of Project. Since they both relate to time, people naturally think they are the same. Time and time again in this newsgroup we have explained the difference and my guess is that we will have to keep explaining it. And yes, I hope the original poster checks out the whole thread. His post wasn't all that definitive. The tasks could either represent completion milestones, as I assumed, or could in fact be a day of effort, as you indicated. Either way, if I knew the larger context, I could be of more help. John Project MVP |
|
|||
|
Re: Displaying actual working days on "Duration" column
Hi,
I'm probably a too simple person, but I think he just took my formula and was happy :-) -- Jan De Messemaeker Microsoft Project Most Valuable Professional +32 495 300 620 For availability check: http://users.online.be/prom-ade/Calendar.pdf "John" <mjensen@theriver.com> wrote in message news:mjensen-A1E16F.08183818072008@msnews.microsoft.com... > In article <1o3mmuzibstfj.15e5s3eygo5pe.dlg@40tude.net>, > salgud <spamboy6547@comcast.net> wrote: > >> On Thu, 17 Jul 2008 20:32:42 -0700, John wrote: >> >> > In article <u7cthlsm5ujo.dk615snvadfl$.dlg@40tude.net>, >> > salgud <spamboy6547@comcast.net> wrote: >> > >> >> On Thu, 17 Jul 2008 07:52:32 -0700, John wrote: >> >> >> >>> In article <6035DFC4-9E23-4047-8AEF-D67C43898AF1@microsoft.com>, >> >>> NLC <NLC@discussions.microsoft.com> wrote: >> >>> >> >>>> Hi, I am trying to have the duration Column to calculate the actual >> >>>> number >> >>>> of >> >>>> working days (not sure if it's the right term I'm using). >> >>>> >> >>>> For example, I have a task summary named "Materials on Site", under >> >>>> this >> >>>> task I have 2 indented tasks that each have duration of 1 day, 3 >> >>>> days >> >>>> apart >> >>>> each other. >> >>>> >> >>>> - Materials on Site >> >>>>>task 1 (08/Jun/10 - 08/Jun/10) duration 1 day >> >>>>>task 2 (08/Jun/14 - 08/Jun/14) duration 1 day >> >>>> >> >>>> By default Project shows a duration of 5 days (10,11,12,13,14) for >> >>>> the >> >>>> task >> >>>> summary, how do i set it to display the actual days required? (which >> >>>> is >> >>>> 2 >> >>>> days) >> >>>> >> >>>> I hope this is clear, thanks a lot! >> >>> >> >>> NLC, >> >>> OK, let me throw my 2 cents into this one also. Jan provided an easy >> >>> way >> >>> to get a summation of what you think you want. However, from your >> >>> description, (i.e. materials on site), what you want is not duration >> >>> and >> >>> it is not work effort as Salgud indicated. >> >>> >> >>> What you really appear to be tracking is the arrival of materials on >> >>> site. That is a milestone and it's duration should be "0'd, probably >> >>> the >> >>> end of the day on June 10th and June 14th. Why in the world you want >> >>> to >> >>> try and sum those up I have no idea - I guess we'd need to understand >> >>> the larger intent. >> >>> >> >>> For milestones, duration at the summary level really has no meaning >> >>> other than the time span in working days between the milestones. >> >>> >> >>> John >> >>> Project MVP >> >> >> >> In a case like this one, I consider it work effort. It's being done >> >> outside >> >> the scheduling organization, so it's being tracked at a higher level >> >> than >> >> at the resource level. In some cases, it could be considered a >> >> milestone >> >> and tracked accordingly. However, tracking it as a milestone gives you >> >> no >> >> control other than to reschedule it if necessary. >> >> In others situations, it can be tracked as the OP is doing. He might >> >> want >> >> to know if the first part of the effort is delayed so he can make >> >> adjustments to the lag or the second part of the effort. In such a >> >> case, >> >> the 1d and 2d durations can be considered work effort, since no >> >> tracking >> >> of >> >> actual resources is occurring but they want to track whether it's all >> >> happening on schedule. It's more flexible this way. >> > >> > Salgud, >> > I'm not sure what you mean by work effort being, "... tracked at a >> > higher level than at the resource level", since that doesn't make too >> > much sense. Work effort with no resources to do it? >> > >> > OK, let's assume for the moment that what the poster is really trying >> > to >> > say is that he has two performance tasks that when completed, will >> > provide materials on site. If that is the case then indeed there is >> > work >> > effort to provide those materials but the poster is confusing duration >> > with work. In Project duration and work are two completely different >> > concepts. Duration is the time span during which tasks are worked. Work >> > is the actual effort required by one or more resources to complete the >> > task. Given this assumption what the poster should be displaying is the >> > Work field. At the summary level that will sum up to the 2 day total - >> > assuming he has assigned one or more resources to perform 8 hours of >> > work on tasks 1 & 2. >> > >> > John >> > Project MVP >> >> Thanks for the detailed explanation of duration and work. Who would have >> thought? >> Seriously, I think you just said in a very convoluted way, what I said >> above. Hopefully, it helped the OP. > > Salgud, > Confusing duration and work is a very common mistake for new users of > Project. Since they both relate to time, people naturally think they are > the same. Time and time again in this newsgroup we have explained the > difference and my guess is that we will have to keep explaining it. > > And yes, I hope the original poster checks out the whole thread. His > post wasn't all that definitive. The tasks could either represent > completion milestones, as I assumed, or could in fact be a day of > effort, as you indicated. Either way, if I knew the larger context, I > could be of more help. > > John > Project MVP |
![]() |
|
| Thread Tools | Search this Thread |
| Display Modes | |
|
|