Go Back   { mindfrost82.com } > Gadget Corner > Tech Newsgroups > Microsoft > MS Office > Project

Reply
 
LinkBack Thread Tools Search this Thread Display Modes
  #1 (permalink)  
Old 07-17-2008, 06:21 PM
=?Utf-8?B?UFM=?=
 
Posts: n/a
Micosoft Project 2007 - Visual Reports

Hi

Is there any way to change the chart exported for earned value over time
from years and quarters to calendar dates? If so, how can this be done?

Thanks.

Reply With Quote
  #2 (permalink)  
Old 07-17-2008, 06:52 PM
JulieS
 
Posts: n/a
Re: Micosoft Project 2007 - Visual Reports

Hello PS,

The information in the chart is from the excel pivot table. If you
expand the quarters and weeks it shows days. You need to make sure
you specify the appropriate measurement when you create the cube. You
can modify the chart by modifying the pivot table.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project

"PS" <PS@discussions.microsoft.com> wrote in message
news:FFF2757F-8311-49FF-B3CE-C5BEB9314AF3@microsoft.com...
> Hi
>
> Is there any way to change the chart exported for earned value over
> time
> from years and quarters to calendar dates? If so, how can this be
> done?
>
> Thanks.
>



Reply With Quote
  #3 (permalink)  
Old 07-18-2008, 03:30 PM
=?Utf-8?B?UFM=?=
 
Posts: n/a
Re: Micosoft Project 2007 - Visual Reports

Hi Julie,

Thanks for your reply - I am aware that if I select days in the view reports
dialog box and expand the pivot table I can see days but what I actually want
to do is be able to select weeks in the view reports dialog box and see the
first calendar date of the week for each week on the chart (like in MS
Project 2003 with the analyzed time scale data function).

Is there a way I can do that without having to select days in the view
reports dialog box?

"JulieS" wrote:

> Hello PS,
>
> The information in the chart is from the excel pivot table. If you
> expand the quarters and weeks it shows days. You need to make sure
> you specify the appropriate measurement when you create the cube. You
> can modify the chart by modifying the pivot table.
>
> I hope this helps. Let us know how you get along.
>
> Julie
> Project MVP
>
> Visit http://project.mvps.org/ for the FAQs and additional information
> about Microsoft Project
>
> "PS" <PS@discussions.microsoft.com> wrote in message
> news:FFF2757F-8311-49FF-B3CE-C5BEB9314AF3@microsoft.com...
> > Hi
> >
> > Is there any way to change the chart exported for earned value over
> > time
> > from years and quarters to calendar dates? If so, how can this be
> > done?
> >
> > Thanks.
> >

>
>
>

Reply With Quote
  #4 (permalink)  
Old 07-18-2008, 03:53 PM
JulieS
 
Posts: n/a
Re: Micosoft Project 2007 - Visual Reports

Hello PS,

To the best of my knowledge, no. The date format in the Excel pivot
table seems to be generated in some semi-mysterious way. I've yet to
figure out exactly where it is getting the labels from -- it isn't the
week number of the year nor week number of the project (from start).
The only method I know of is to manually enter the data you wish to
see in the pivot table.

Julie

"PS" <PS@discussions.microsoft.com> wrote in message
news:73288E47-ECE0-4197-9D1F-5811CADF052A@microsoft.com...
> Hi Julie,
>
> Thanks for your reply - I am aware that if I select days in the view
> reports
> dialog box and expand the pivot table I can see days but what I
> actually want
> to do is be able to select weeks in the view reports dialog box and
> see the
> first calendar date of the week for each week on the chart (like in
> MS
> Project 2003 with the analyzed time scale data function).
>
> Is there a way I can do that without having to select days in the
> view
> reports dialog box?
>
> "JulieS" wrote:
>
>> Hello PS,
>>
>> The information in the chart is from the excel pivot table. If you
>> expand the quarters and weeks it shows days. You need to make sure
>> you specify the appropriate measurement when you create the cube.
>> You
>> can modify the chart by modifying the pivot table.
>>
>> I hope this helps. Let us know how you get along.
>>
>> Julie
>> Project MVP
>>
>> Visit http://project.mvps.org/ for the FAQs and additional
>> information
>> about Microsoft Project
>>
>> "PS" <PS@discussions.microsoft.com> wrote in message
>> news:FFF2757F-8311-49FF-B3CE-C5BEB9314AF3@microsoft.com...
>> > Hi
>> >
>> > Is there any way to change the chart exported for earned value
>> > over
>> > time
>> > from years and quarters to calendar dates? If so, how can this
>> > be
>> > done?
>> >
>> > Thanks.
>> >

>>
>>
>>



Reply With Quote
Reply

  { mindfrost82.com } > Gadget Corner > Tech Newsgroups > Microsoft > MS Office > Project


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On



All times are GMT. The time now is 11:28 PM.


Powered by vBulletin, Copyright ©2000 - 2008, Jelsoft Enterprises Ltd.
Search Engine Friendly URLs by vBSEO 3.1.0 ©2007, Crawlability, Inc.
© 1999-2008 mindfrost82.com v11.0

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108