Re: Locking dates in Project 2003
Hello Veronica,
You can certainly copy and paste the dates to a spare date field or use one of the baseline fields for this, but if you have information in one of the fields Project uses for calculations (Start, Finish) the answer is no. I hope this helps. Let us know how you get along. Julie Project MVP Visit http://project.mvps.org/ for the FAQs and additional information about Microsoft Project "Veronica" <Veronica@discussions.microsoft.com> wrote in message news:93F34347-EA1B-4652-A214-B9DB68395346@microsoft.com... > Is there any way to lock dates that have been previously calculated > in > Project 2003? |
![]() |
|