In Office Project Web Access, I had made a series of updates to some tasks
and then submitted them to the project manager. However these updates were
rejected and the project manager then made a series of more accurate updates
to all the tasks I had previously submitted.

In the My Tasks view, all I can see is that the updates I made to the tasks
were rejected, and the tasks still show the changes I attempted to make. It
seems to be prompting me to resubmit my changes, as it says "updates not yet
submitted"

However, I would just like to see the official updates the project manager
has made. Basically I would like to just revert my changes, or accept the
rejection of my changes by my manager so I can see the new updates.

Is there any way to do this?
Reply With Quote
  #2 (permalink)  
Old 07-18-2008, 05:07 PM
Dale Howard [MVP]
 
Posts: n/a
Re: reverting task updates

poru --

In the future, please post your Project Server questions in the
microsoft.public.project.server newsgroup, as this newsgroup is dedicated to
the Microsoft Project desktop application only. To see your PMs updates,
he/she simply needs to publish the latest schedule changes using one of the
following methods:

1. Project Server 2007: click File - Publish.
2. Project Server 2003: Click Collaborate - Publish - Republish
Assignments. Select the "Ovewrite actual work entered by resources" option
and click OK.

Thus, the solution does not belong to you, but to your PM. Hope this helps.

--
Dale A. Howard [MVP]
VP of Educational Services
msProjectExperts
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We write the books on Project Server"


"poru" <poru@discussions.microsoft.com> wrote in message
news:204DB657-14E5-4778-962B-F130931D1F80@microsoft.com...
> In Office Project Web Access, I had made a series of updates to some tasks
> and then submitted them to the project manager. However these updates
> were
> rejected and the project manager then made a series of more accurate
> updates
> to all the tasks I had previously submitted.
>
> In the My Tasks view, all I can see is that the updates I made to the
> tasks
> were rejected, and the tasks still show the changes I attempted to make.
> It
> seems to be prompting me to resubmit my changes, as it says "updates not
> yet
> submitted"
>
> However, I would just like to see the official updates the project manager
> has made. Basically I would like to just revert my changes, or accept the
> rejection of my changes by my manager so I can see the new updates.
>
> Is there any way to do this?


Reply With Quote
Reply

  { mindfrost82.com } > Gadget Corner > Tech Newsgroups > Microsoft > MS Office > Project


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On



All times are GMT. The time now is 08:33 AM.


Powered by vBulletin, Copyright ©2000 - 2008, Jelsoft Enterprises Ltd.
Search Engine Friendly URLs by vBSEO 3.1.0 ©2007, Crawlability, Inc.
© 1999-2008 mindfrost82.com v11.0

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109