![]() |
|
|
|||
|
Tasks in Parallel
Hi,
1. I have three phases (Construction, Code Review, and Unit Testing). 2. The two phases (Code Review and Unit Testing) should run in parallel with Construction 3. The start date and end date for this trunk is from 1-Aug-2008 to 7- Aug-2008 respectively 4. There are two resources; R1 would handle development, R2 would handle code review and testing 5. The efforts are perfect for construction phase I would like to if I could accomplish this:- 6. Need to add a task Code review and assign the start date from 1-Aug to 7-Aug and assign this task to R2 without changing the parent effort duration 7. Need to add another task Unit Testing and assign the start date from 1-Aug to 7-Aug and assign this task to R2 without changing the parent effort duration I am using MS Project 2003. Kindly help! Thank you, Dev |
|
|||
|
RE: Tasks in Parallel
It is unclear what you mean by "without changing the parent effort duration"
Duration is a specific term in project. It means how long a task goes on. effort is also a specific term, but not well defined in Project. You could make a case that it equals work or that it means resources. If effort = resource and duration is duration then effort duration would equal work. And the answer is that if you make a non-zero unit assignment of a resource to a task, then the total work will increase. In that case the answer to your question is no. If you meant something different by your question, then the answer may be different too. -Jack Dahlgren "Dev" wrote: > Hi, > > 1. I have three phases (Construction, Code Review, and Unit Testing). > 2. The two phases (Code Review and Unit Testing) should run in > parallel with Construction > 3. The start date and end date for this trunk is from 1-Aug-2008 to 7- > Aug-2008 respectively > 4. There are two resources; R1 would handle development, R2 would > handle code review and testing > 5. The efforts are perfect for construction phase > > I would like to if I could accomplish this:- > 6. Need to add a task Code review and assign the start date from 1-Aug > to 7-Aug and assign this task to R2 without changing the parent effort > duration > 7. Need to add another task Unit Testing and assign the start date > from 1-Aug to 7-Aug and assign this task to R2 without changing the > parent effort duration > > I am using MS Project 2003. > > Kindly help! > > Thank you, > Dev > |
|
|||
|
Re: Tasks in Parallel
Hi,
Thank you and sorry for the confusion. here is the sample: 1. Only one resource Project 0.8 wks Release 1 0.8 wks Trunk 1 0.8 wks This is fine and this is what is expected. 2. Multiple resource: I would want to run other phases parallely and assign the task to another resource. Project 1 wk Release 1 1 wk Trunk 1 1 wk Code review 9 hours added and assigned to different resource Problem 1: - The total duration for trunk, release and project should not be increased. this is becuase the tasks are done in parallel and is assigned to different resource - Unable to set the start and end date for code review as the trunk start date and trunk end date. A constraint start no earlier than 1- Aug is set for this task. When the end date is set to 7-Aug, the duration for the task spikes automatically. Hope the problem is understood. Thank you so much for your help! -Dev On Jul 18, 3:38*pm, Jack Dahlgren <JackDahlg...@discussions.microsoft.com> wrote: > It is unclear what you mean by "without changing the parent effort duration" > > Duration is a specific term in project. It means how long a task goes on. > effort is also a specific term, but not well defined in Project. You could > make a case that it equals work or that it means resources. > > If effort = resource and duration is duration then effort duration would > equal work. > And the answer is that if you make a non-zero unit assignment of a resource > to a task, then the total work will increase. > > In that case the answer to your question is no. If you meant something > different by your question, then the answer may be different too. > > -Jack Dahlgren > > > > "Dev" wrote: > > Hi, > > > 1. I have three phases (Construction, Code Review, and Unit Testing). > > 2. The two phases (Code Review and Unit Testing) should run in > > parallel with Construction > > 3. The start date and end date for this trunk is from 1-Aug-2008 to 7- > > Aug-2008 respectively > > 4. There are two resources; R1 would handle development, R2 would > > handle code review and testing > > 5. The efforts are perfect for construction phase > > > I would like to if I could accomplish this:- > > 6. Need to add a task Code review and assign the start date from 1-Aug > > to 7-Aug and assign this task to R2 without changing the parent effort > > duration > > 7. Need to add another task Unit Testing and assign the start date > > from 1-Aug to 7-Aug and assign this task to R2 without changing the > > parent effort duration > > > I am using MS Project 2003. > > > Kindly help! > > > Thank you, > > Dev- Hide quoted text - > > - Show quoted text - |
![]() |
|
| Thread Tools | Search this Thread |
| Display Modes | |
|
|