Linking external issue IDs to a task in MS Project 2003 server

I'd like to link issue ID's from a 3rd party issue trackign system to tasks
within the MS Project 2003 PWA. The issue IDs will need to be visible to the
user and since they are created externally, will need to be linkable to
multiple projects/tasks. Is this possible?
Reply With Quote
  #2 (permalink)  
Old 07-21-2008, 08:08 PM
Mike Glen
 
Posts: n/a
Re: Linking external issue IDs to a task in MS Project 2003 server

Hi Lnagl,

Try posting on the microsoft.public.project.server newsgroup. Please see
FAQ Item: 24. Project Newsgroups. FAQs, companion products and other
useful Project information can be seen at this web address:
http://project.mvps.org/faqs.htm

Mike Glen
Project MVP


lnagl wrote:
> I'd like to link issue ID's from a 3rd party issue trackign system to
> tasks within the MS Project 2003 PWA. The issue IDs will need to be
> visible to the user and since they are created externally, will need
> to be linkable to multiple projects/tasks. Is this possible?



Reply With Quote
  #3 (permalink)  
Old 07-21-2008, 09:04 PM
=?Utf-8?B?bG5hZ2w=?=
 
Posts: n/a
Re: Linking external issue IDs to a task in MS Project 2003 server

thanks, will do.

"Mike Glen" wrote:

> Hi Lnagl,
>
> Try posting on the microsoft.public.project.server newsgroup. Please see
> FAQ Item: 24. Project Newsgroups. FAQs, companion products and other
> useful Project information can be seen at this web address:
> http://project.mvps.org/faqs.htm
>
> Mike Glen
> Project MVP
>
>
> lnagl wrote:
> > I'd like to link issue ID's from a 3rd party issue trackign system to
> > tasks within the MS Project 2003 PWA. The issue IDs will need to be
> > visible to the user and since they are created externally, will need
> > to be linkable to multiple projects/tasks. Is this possible?

>
>
>

Reply With Quote
  #4 (permalink)  
Old 07-21-2008, 10:02 PM
Mike Glen
 
Posts: n/a
Re: Linking external issue IDs to a task in MS Project 2003 server

You're welcome, lnagl, and good luck :-)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials

wrote:
> thanks, will do.
>
> "Mike Glen" wrote:
>
>> Hi Lnagl,
>>
>> Try posting on the microsoft.public.project.server newsgroup.
>> Please see FAQ Item: 24. Project Newsgroups. FAQs, companion
>> products and other useful Project information can be seen at this
>> web address: http://project.mvps.org/faqs.htm
>>
>> Mike Glen
>> Project MVP
>>
>>
>> lnagl wrote:
>>> I'd like to link issue ID's from a 3rd party issue trackign system
>>> to tasks within the MS Project 2003 PWA. The issue IDs will need
>>> to be visible to the user and since they are created externally,
>>> will need to be linkable to multiple projects/tasks. Is this
>>> possible?



Reply With Quote
Reply

  { mindfrost82.com } > Gadget Corner > Tech Newsgroups > Microsoft > MS Office > Project


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On



All times are GMT. The time now is 07:51 AM.


Powered by vBulletin, Copyright ©2000 - 2008, Jelsoft Enterprises Ltd.
Search Engine Friendly URLs by vBSEO 3.1.0 ©2007, Crawlability, Inc.
© 1999-2008 mindfrost82.com v11.0

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108