"Actual work" and "Work" in Task Updates screen shows different va
If updating task progress (for a 2 day 15 hour task, fixed work, 7.5 hr
working day) using Outlook or Web access and submitting the selected task then the manager (under Task Updates) sees actual work, for example 7.5 hours, on the left hand side of the split screen (and 7.5 remaining) but only 7 hours on the right hand side summary for both work and actual for that day, giving only 14.5 for the job. If the user types 8 hours work done the first day, then the manager sees 7.75 hours of both work and actual work on the right hand side for that day and 0.25h actual work for the second day. What is happening? many thanks, M. How do I attach screen dumps to help explain this? If the schedule is adhered as projected the shouldn't the total remain the same, and for fixed work sholdn't the total stay the same, i.e if more hours are done first day there should be less the next day to do. |
|
|||
|
Re: "Actual work" and "Work" in Task Updates screen shows different va
Hi MswT,
Try posting on the microsoft.public.project.server newsgroup. Please see FAQ Item: 24. Project Newsgroups. FAQs, companion products and other useful Project information can be seen at this web address: http://project.mvps.org/faqs.htm Mike Glen Project MVP MswT wrote: > If updating task progress (for a 2 day 15 hour task, fixed work, 7.5 > hr working day) using Outlook or Web access and submitting the > selected task then the manager (under Task Updates) sees actual work, > for example 7.5 hours, on the left hand side of the split screen (and > 7.5 remaining) but only 7 hours on the right hand side summary for > both work and actual for that day, giving only 14.5 for the job. If > the user types 8 hours work done the first day, then the manager sees > 7.75 hours of both work and actual work on the right hand side for > that day and 0.25h actual work for the second day. > > What is happening? many thanks, M. > > How do I attach screen dumps to help explain this? > > If the schedule is adhered as projected the shouldn't the total > remain the same, and for fixed work sholdn't the total stay the same, > i.e if more hours are done first day there should be less the next > day to do. |
![]() |
|
| Thread Tools | Search this Thread |
| Display Modes | |
|
|