Exporting to Excel and Maintining Task Hierarchy / Font Formatting

I have a project plan that I need to send to folks who do not have MS
Project. They want it in Excel format but when I export all of the
tasks, the result is an unformatted Excel worksheet. It's really
difficult to see summary tasks, etc. this way.

Also, it would be nice if the export to Excel included the calculated
fields, e.g. the Summary Tasks, Dates. . .
Reply With Quote
  #2 (permalink)  
Old 07-22-2008, 01:20 PM
JulieS
 
Posts: n/a
Re: Exporting to Excel and Maintining Task Hierarchy / Font Formatting

Hello seven-percent,

Fellow MVP Jack Dahlgren has kindly made a sample macro available
which exports the task hierarchy. See:

http://masamiki.com/project/macros.htm

and look for the Export hierarchy to Excel macro.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project


"seven_percent" <Daniel.Gullo@gmail.com> wrote in message
news:2c70fb93-9997-4dbd-b6f9-5ef8c82f64ee@27g2000hsf.googlegroups.com...
>I have a project plan that I need to send to folks who do not have MS
> Project. They want it in Excel format but when I export all of the
> tasks, the result is an unformatted Excel worksheet. It's really
> difficult to see summary tasks, etc. this way.
>
> Also, it would be nice if the export to Excel included the
> calculated
> fields, e.g. the Summary Tasks, Dates. . .



Reply With Quote
  #3 (permalink)  
Old 07-22-2008, 07:40 PM
Jim Spiller
 
Posts: n/a
Re: Exporting to Excel and Maintining Task Hierarchy / Font Formatting

If you have version prior to Project 2007 try saving the project as a web
page and opening the corresponding .html file in Excel. Looks a bit
better...


"seven_percent" <Daniel.Gullo@gmail.com> wrote in message
news:2c70fb93-9997-4dbd-b6f9-5ef8c82f64ee@27g2000hsf.googlegroups.com...
>I have a project plan that I need to send to folks who do not have MS
> Project. They want it in Excel format but when I export all of the
> tasks, the result is an unformatted Excel worksheet. It's really
> difficult to see summary tasks, etc. this way.
>
> Also, it would be nice if the export to Excel included the calculated
> fields, e.g. the Summary Tasks, Dates. . .



Reply With Quote
Reply

  { mindfrost82.com } > Gadget Corner > Tech Newsgroups > Microsoft > MS Office > Project


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On



All times are GMT. The time now is 06:03 PM.


Powered by vBulletin, Copyright ©2000 - 2008, Jelsoft Enterprises Ltd.
Search Engine Friendly URLs by vBSEO 3.1.0 ©2007, Crawlability, Inc.
© 1999-2008 mindfrost82.com v11.0

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109