Resource overallocation problem
We are trying to use MS project to make production schedule for our
truck body jobs. As all jobs are similar, must go through different workcenters, we take different jobs as tasks and workcenters as subtasks. For each workcenter (subtask), we have relatively stable workers (resources). I already made groups by workcenters for these resources. We don't want to assign specific resources to subtasks, because we don't care who would do the job. Anyone in the group would be ok. So I try to assign groups on subtasks, but many resources are overallocated. Then I try to build a resource pool, and share resources for different subtasks, but it seems it still doesn't work. Many resources are still overallocated. What should I do to make sure the resources are not overallocated for different subtasks? Is that the proper way to use 'share resource'? Or is there a better way to solve the problem or easy for us to schedule? Please help. Thanks, Tracey |
|
|||
|
Re: Resource overallocation problem
Hi,
Do you use 1 file per job all all in 1 file? If all in 1 file then resoruce sharing is irrelevant. The answer is you should use resource leveling to do away with the overallocations. Reads teh principles and give it a try; do come back here for details if necessary. HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional +32 495 300 620 For availability check: http://users.online.be/prom-ade/Calendar.pdf <xinxindong2004@gmail.com> wrote in message news:74c2f53f-c89a-4ba8-bd43-e26ae86c718d@a1g2000hsb.googlegroups.com... > We are trying to use MS project to make production schedule for our > truck body jobs. As all jobs are similar, must go through different > workcenters, we take different jobs as tasks and workcenters as > subtasks. > > For each workcenter (subtask), we have relatively stable workers > (resources). I already made groups by workcenters for these resources. > We don't want to assign specific resources to subtasks, because we > don't care who would do the job. Anyone in the group would be ok. So I > try to assign groups on subtasks, but many resources are > overallocated. Then I try to build a resource pool, and share > resources for different subtasks, but it seems it still doesn't work. > Many resources are still overallocated. What should I do to make sure > the resources are not overallocated for different subtasks? Is that > the proper way to use 'share resource'? Or is there a better way to > solve the problem or easy for us to schedule? > > Please help. > Thanks, > Tracey |
|
|||
|
Re: Resource overallocation problem
On Jul 22, 11:41*am, "Jan De Messemaeker" <janremovet...@prom-ade.be>
wrote: > Hi, > > Do you use 1 file per job all all in 1 file? > If all in 1 file then resoruce sharing is irrelevant. > The answer is you should use resource leveling to do away with the > overallocations. > Reads teh principles and give it a try; do come back here for details if > necessary. > HTH > > -- > Jan De Messemaeker > Microsoft Project Most Valuable Professional > +32 495 300 620 > For availability check:http://users.online.be/prom-ade/Calendar.pdf<xinxindong2...@gmail.com> wrote in message > > news:74c2f53f-c89a-4ba8-bd43-e26ae86c718d@a1g2000hsb.googlegroups.com... > > > > > We are trying to use MS project to make production schedule for our > > truck body jobs. As all jobs are similar, must go through different > > workcenters, we take different jobs as tasks and workcenters as > > subtasks. > > > For each workcenter (subtask), we have relatively stable workers > > (resources). I already made groups by workcenters for these resources. > > We don't want to assign specific resources to subtasks, because we > > don't care who would do the job. Anyone in the group would be ok. So I > > try to assign groups on subtasks, but many resources are > > overallocated. Then I try to build a resource pool, and share > > resources for different subtasks, but it seems it still doesn't work. > > Many resources are still overallocated. What should I do to make sure > > the resources are not overallocated for different subtasks? Is that > > the proper way to use 'share resource'? Or is there a better way to > > solve the problem or easy for us to schedule? > > > Please help. > > Thanks, > > Tracey- Hide quoted text - > > - Show quoted text - Hi, Jan, I put all in one file, and had a try on level resource. It works. Thanks. I have another question. If we don't care who would do the job and just pick one or two persons to do the job at the time, then how should I assign resources? If assigning the group instead of individuals, the duration would be much shorter than it actually is. Is there a easy way to do that? We don't want to specify some individuals to the job. We hope to assign labor time in the group instead of individuals. Is that possible? Please help. Thanks, Tracey |
|
|||
|
Re: Resource overallocation problem
Yes, you can call the resource Workers, or Electricians or whatever and in
the Resource Usage view, assign the Max Units to reflect your situation eg: 300% for 3 workers or whatever numbers you have. Then assign that resource to the tasks and then level. Project will then level assuming you have no more than the Max Units you set. However, you can't then assign one of them by name - it's one or the other. Hope this helps - please let us know how you get on ![]() Mike Glen MS Project MVP See http://tinyurl.com/2xbhc for my free Project Tutorials ============= I have another question. If we don't care who would do the job and just pick one or two persons to do the job at the time, then how should I assign resources? If assigning the group instead of individuals, the duration would be much shorter than it actually is. Is there a easy way to do that? We don't want to specify some individuals to the job. We hope to assign labor time in the group instead of individuals. Is that possible? Please help. Thanks, Tracey |
|
|||
|
Re: Resource overallocation problem
On Aug 1, 9:02*am, "Mike Glen" <glenATmvps.org> wrote:
> Yes, you can call the resource Workers, or Electricians or whatever and in > the Resource Usage view, assign the Max Units to reflect your situation eg: > 300% for 3 workers or whatever numbers you have. *Then assign that resource > to the tasks and then level. *Project will then level assuming you haveno > more than the Max Units you set. *However, you can't then assign one ofthem > by name - it's one or the other. > > Hope this helps - please let us know how you get on ![]() > > Mike Glen > MS Project MVP > Seehttp://tinyurl.com/2xbhcfor my free Project Tutorials > > ============= Hi, Mike, I understand what you said. But if some people in the group take vacation, how it would reflect to the Max units. Do I have to do it manually? Is there a way I input the exceptional days for different workers, and Max units for the group would be changed automatically? Please help. Thanks, Tracey |
|
|||
|
Re: Resource overallocation problem
Hi Tracey,
Sorry for the delay - I've been away. If you wish to allow for holidays, etc, you will have to manually adjust the avilability contour in the resource Availability dialog (double-click the resource name on the Resource Sheet view). When using generic resources in this way, you cannot control an individual's availability in any other way that I'm aware of. Mike Glen Project MVP xinxindong2004@gmail.com wrote: > On Aug 1, 9:02 am, "Mike Glen" <glenATmvps.org> wrote: >> Yes, you can call the resource Workers, or Electricians or whatever >> and in the Resource Usage view, assign the Max Units to reflect your >> situation eg: 300% for 3 workers or whatever numbers you have. Then >> assign that resource to the tasks and then level. Project will then >> level assuming you have no more than the Max Units you set. However, >> you can't then assign one of them by name - it's one or the other. >> >> Hope this helps - please let us know how you get on ![]() >> >> Mike Glen >> MS Project MVP >> Seehttp://tinyurl.com/2xbhcfor my free Project Tutorials >> >> ============= > > Hi, Mike, > > I understand what you said. But if some people in the group take > vacation, how it would reflect to the Max units. Do I have to do it > manually? Is there a way I input the exceptional days for different > workers, and Max units for the group would be changed automatically? > Please help. > > Thanks, > Tracey |
|
|||
|
Re: Resource overallocation problem
On Aug 10, 2:30*pm, "Mike Glen" <glenATmvps.org> wrote:
> Hi Tracey, > > Sorry for the delay - I've been away. *If you wish to allow for holidays, > etc, you will have to manually adjust the avilability contour in the > resource Availability dialog (double-click the resource name on the Resource > Sheet view). *When using generic resources in this way, you cannot control > an individual's availability in any other way that I'm aware of. > > Mike Glen > Project MVP > > > > xinxindong2...@gmail.com wrote: > > On Aug 1, 9:02 am, "Mike Glen" <glenATmvps.org> wrote: > >> Yes, you can call the resource Workers, or Electricians or whatever > >> and in the Resource Usage view, assign the Max Units to reflect your > >> situation eg: 300% for 3 workers or whatever numbers you have. Then > >> assign that resource to the tasks and then level. Project will then > >> level assuming you have no more than the Max Units you set. However, > >> you can't then assign one of them by name - it's one or the other. > > >> Hope this helps - please let us know how you get on ![]() > > >> Mike Glen > >> MS Project MVP > >> Seehttp://tinyurl.com/2xbhcformy free Project Tutorials > > >> ============= > > > Hi, Mike, > > > I understand what you said. But if some people in the group take > > vacation, how it would reflect to the Max units. Do I have to do it > > manually? Is there a way I input the exceptional days for different > > workers, and Max units for the group would be changed automatically? > > Please help. > > > Thanks, > > Tracey- Hide quoted text - > > - Show quoted text - Hi Mike, Thanks for your help. If you consider our situation from the beginning, the repetition job environment, the information for total labor time in the coming weeks, would you help me to figure out a better way to make the schedule? I am thinking probably you would have an efficient way to do this, instead of assigning individuals or max unit of groups to tasks. Thanks, Tracey |
|
|||
|
Re: Resource overallocation problem
Hi Tracey,
There is a better way and that is to use a program that's designed for controlling production Project is designed for those once only, uniqueundertakings with a clearly defined start and finish. You can't use individual calendars for a group, but you can use a group calendar, but I don't believe that will be of use to you. Max units is the only way to go, and varying the units by time to meet you resource absences is your only sensible option with Project. Other than that, I believe you are in danger of micro-managing. Except for major absences like holidays or longer-term sickness, leave the Max Units alone. Project is a scheduling program based on the estimated times you enter. Be more generous with your estimates and let the local management ( foreman?) fit the workers into their slots. If your tasks really are repetitive, you can then refine your estimates. Mike Glen Project MVP <xinxindong2004@gmail.com> wrote in message news:32a15468-f8f9-4df5-906a-52bd616eaf6d@p31g2000prf.googlegroups.com... On Aug 10, 2:30 pm, "Mike Glen" <glenATmvps.org> wrote: > Hi Tracey, > > Sorry for the delay - I've been away. If you wish to allow for holidays, > etc, you will have to manually adjust the avilability contour in the > resource Availability dialog (double-click the resource name on the > Resource > Sheet view). When using generic resources in this way, you cannot control > an individual's availability in any other way that I'm aware of. > > Mike Glen > Project MVP > > > > xinxindong2...@gmail.com wrote: > > On Aug 1, 9:02 am, "Mike Glen" <glenATmvps.org> wrote: > >> Yes, you can call the resource Workers, or Electricians or whatever > >> and in the Resource Usage view, assign the Max Units to reflect your > >> situation eg: 300% for 3 workers or whatever numbers you have. Then > >> assign that resource to the tasks and then level. Project will then > >> level assuming you have no more than the Max Units you set. However, > >> you can't then assign one of them by name - it's one or the other. > > >> Hope this helps - please let us know how you get on ![]() > > >> Mike Glen > >> MS Project MVP > >> Seehttp://tinyurl.com/2xbhcformy free Project Tutorials > > >> ============= > > > Hi, Mike, > > > I understand what you said. But if some people in the group take > > vacation, how it would reflect to the Max units. Do I have to do it > > manually? Is there a way I input the exceptional days for different > > workers, and Max units for the group would be changed automatically? > > Please help. > > > Thanks, > > Tracey- Hide quoted text - > > - Show quoted text - Hi Mike, Thanks for your help. If you consider our situation from the beginning, the repetition job environment, the information for total labor time in the coming weeks, would you help me to figure out a better way to make the schedule? I am thinking probably you would have an efficient way to do this, instead of assigning individuals or max unit of groups to tasks. Thanks, Tracey |
|
|||
|
Re: Resource overallocation problem
Thanks, Mike.
![]() Just like you said, our schedule is not so strict and I don't have to make a perfect one. Right now we do everything manually, just want to use project to save some time for scheduling. Thanks again. Tracey On Aug 13, 2:13*am, "Mike Glen" <glenATmvps.org> wrote: > Hi Tracey, > > There is a better way and that is to use a program that's designed for > controlling production *Project is designed for those once only, unique> undertakings with a clearly defined start and finish. *You can't use > individual calendars for a group, but you can use a group calendar, but I > don't believe that will be of use to you. Max units is the only way to go, > and varying the units by time to meet you resource absences is your only > sensible option with Project. > > Other than that, I believe you are in danger of micro-managing. *Exceptfor > major absences like holidays or longer-term sickness, *leave the Max Units > alone. *Project is a scheduling program based on the estimated times you > enter. *Be more generous with your estimates and let the local management > ( foreman?) fit the workers into their slots. *If your tasks really are > repetitive, you can then refine your estimates. > > Mike Glen > Project MVP > > <xinxindong2...@gmail.com> wrote in message > > news:32a15468-f8f9-4df5-906a-52bd616eaf6d@p31g2000prf.googlegroups.com... > On Aug 10, 2:30 pm, "Mike Glen" <glenATmvps.org> wrote: > > > > > > > Hi Tracey, > > > Sorry for the delay - I've been away. If you wish to allow for holidays, > > etc, you will have to manually adjust the avilability contour in the > > resource Availability dialog (double-click the resource name on the > > Resource > > Sheet view). When using generic resources in this way, you cannot control > > an individual's availability in any other way that I'm aware of. > > > Mike Glen > > Project MVP > > > xinxindong2...@gmail.com wrote: > > > On Aug 1, 9:02 am, "Mike Glen" <glenATmvps.org> wrote: > > >> Yes, you can call the resource Workers, or Electricians or whatever > > >> and in the Resource Usage view, assign the Max Units to reflect your > > >> situation eg: 300% for 3 workers or whatever numbers you have. Then > > >> assign that resource to the tasks and then level. Project will then > > >> level assuming you have no more than the Max Units you set. However, > > >> you can't then assign one of them by name - it's one or the other. > > > >> Hope this helps - please let us know how you get on ![]() > > > >> Mike Glen > > >> MS Project MVP > > >> Seehttp://tinyurl.com/2xbhcformyfree Project Tutorials > > > >> ============= > > > > Hi, Mike, > > > > I understand what you said. But if some people in the group take > > > vacation, how it would reflect to the Max units. Do I have to do it > > > manually? Is there a way I input the exceptional days for different > > > workers, and Max units for the group would be changed automatically? > > > Please help. > > > > Thanks, > > > Tracey- Hide quoted text - > > > - Show quoted text - > > Hi Mike, > > Thanks for your help. If you consider our situation from the > beginning, the repetition job environment, the information for total > labor time in the coming weeks, would you help me to figure out a > better way to make the schedule? I am thinking probably you would have > an efficient way to do this, instead of assigning individuals or max > unit of groups to tasks. > > Thanks, > Tracey- Hide quoted text - > > - Show quoted text - |
|
|||
|
Re: Resource overallocation problem
You're welcome, Tracey, and good luck :-)
Mike Glen MS Project MVP See http://tinyurl.com/2xbhc for my free Project Tutorials <xinxindong2004@gmail.com> wrote in message news:93fa3558-375b-4e49-bb4a-b5343044aa63@l33g2000pri.googlegroups.com... Thanks, Mike. ![]() Just like you said, our schedule is not so strict and I don't have to make a perfect one. Right now we do everything manually, just want to use project to save some time for scheduling. Thanks again. Tracey On Aug 13, 2:13 am, "Mike Glen" <glenATmvps.org> wrote: > Hi Tracey, > > There is a better way and that is to use a program that's designed for > controlling production Project is designed for those once only, unique> undertakings with a clearly defined start and finish. You can't use > individual calendars for a group, but you can use a group calendar, but I > don't believe that will be of use to you. Max units is the only way to go, > and varying the units by time to meet you resource absences is your only > sensible option with Project. > > Other than that, I believe you are in danger of micro-managing. Except for > major absences like holidays or longer-term sickness, leave the Max Units > alone. Project is a scheduling program based on the estimated times you > enter. Be more generous with your estimates and let the local management > ( foreman?) fit the workers into their slots. If your tasks really are > repetitive, you can then refine your estimates. > > Mike Glen > Project MVP > > <xinxindong2...@gmail.com> wrote in message > > news:32a15468-f8f9-4df5-906a-52bd616eaf6d@p31g2000prf.googlegroups.com... > On Aug 10, 2:30 pm, "Mike Glen" <glenATmvps.org> wrote: > > > > > > > Hi Tracey, > > > Sorry for the delay - I've been away. If you wish to allow for holidays, > > etc, you will have to manually adjust the avilability contour in the > > resource Availability dialog (double-click the resource name on the > > Resource > > Sheet view). When using generic resources in this way, you cannot > > control > > an individual's availability in any other way that I'm aware of. > > > Mike Glen > > Project MVP > > > xinxindong2...@gmail.com wrote: > > > On Aug 1, 9:02 am, "Mike Glen" <glenATmvps.org> wrote: > > >> Yes, you can call the resource Workers, or Electricians or whatever > > >> and in the Resource Usage view, assign the Max Units to reflect your > > >> situation eg: 300% for 3 workers or whatever numbers you have. Then > > >> assign that resource to the tasks and then level. Project will then > > >> level assuming you have no more than the Max Units you set. However, > > >> you can't then assign one of them by name - it's one or the other. > > > >> Hope this helps - please let us know how you get on ![]() > > > >> Mike Glen > > >> MS Project MVP > > >> Seehttp://tinyurl.com/2xbhcformyfree Project Tutorials > > > >> ============= > > > > Hi, Mike, > > > > I understand what you said. But if some people in the group take > > > vacation, how it would reflect to the Max units. Do I have to do it > > > manually? Is there a way I input the exceptional days for different > > > workers, and Max units for the group would be changed automatically? > > > Please help. > > > > Thanks, > > > Tracey- Hide quoted text - > > > - Show quoted text - > > Hi Mike, > > Thanks for your help. If you consider our situation from the > beginning, the repetition job environment, the information for total > labor time in the coming weeks, would you help me to figure out a > better way to make the schedule? I am thinking probably you would have > an efficient way to do this, instead of assigning individuals or max > unit of groups to tasks. > > Thanks, > Tracey- Hide quoted text - > > - Show quoted text - |
![]() |
|