Resource overallocation problem

We are trying to use MS project to make production schedule for our
truck body jobs. As all jobs are similar, must go through different
workcenters, we take different jobs as tasks and workcenters as
subtasks.

For each workcenter (subtask), we have relatively stable workers
(resources). I already made groups by workcenters for these resources.
We don't want to assign specific resources to subtasks, because we
don't care who would do the job. Anyone in the group would be ok. So I
try to assign groups on subtasks, but many resources are
overallocated. Then I try to build a resource pool, and share
resources for different subtasks, but it seems it still doesn't work.
Many resources are still overallocated. What should I do to make sure
the resources are not overallocated for different subtasks? Is that
the proper way to use 'share resource'? Or is there a better way to
solve the problem or easy for us to schedule?

Please help.
Thanks,
Tracey
Reply With Quote
  #2 (permalink)  
Old 07-22-2008, 06:41 PM
Jan De Messemaeker
 
Posts: n/a
Re: Resource overallocation problem

Hi,

Do you use 1 file per job all all in 1 file?
If all in 1 file then resoruce sharing is irrelevant.
The answer is you should use resource leveling to do away with the
overallocations.
Reads teh principles and give it a try; do come back here for details if
necessary.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
<xinxindong2004@gmail.com> wrote in message
news:74c2f53f-c89a-4ba8-bd43-e26ae86c718d@a1g2000hsb.googlegroups.com...
> We are trying to use MS project to make production schedule for our
> truck body jobs. As all jobs are similar, must go through different
> workcenters, we take different jobs as tasks and workcenters as
> subtasks.
>
> For each workcenter (subtask), we have relatively stable workers
> (resources). I already made groups by workcenters for these resources.
> We don't want to assign specific resources to subtasks, because we
> don't care who would do the job. Anyone in the group would be ok. So I
> try to assign groups on subtasks, but many resources are
> overallocated. Then I try to build a resource pool, and share
> resources for different subtasks, but it seems it still doesn't work.
> Many resources are still overallocated. What should I do to make sure
> the resources are not overallocated for different subtasks? Is that
> the proper way to use 'share resource'? Or is there a better way to
> solve the problem or easy for us to schedule?
>
> Please help.
> Thanks,
> Tracey



Reply With Quote
  #3 (permalink)  
Old 07-31-2008, 11:04 PM
xinxindong2004@gmail.com
 
Posts: n/a
Re: Resource overallocation problem

On Jul 22, 11:41*am, "Jan De Messemaeker" <janremovet...@prom-ade.be>
wrote:
> Hi,
>
> Do you use 1 file per job all all in 1 file?
> If all in 1 file then resoruce sharing is irrelevant.
> The answer is you should use resource leveling to do away with the
> overallocations.
> Reads teh principles and give it a try; do come back here for details if
> necessary.
> HTH
>
> --
> Jan De Messemaeker
> Microsoft Project Most Valuable Professional
> +32 495 300 620
> For availability check:http://users.online.be/prom-ade/Calendar.pdf<xinxindong2...@gmail.com> wrote in message
>
> news:74c2f53f-c89a-4ba8-bd43-e26ae86c718d@a1g2000hsb.googlegroups.com...
>
>
>
> > We are trying to use MS project to make production schedule for our
> > truck body jobs. As all jobs are similar, must go through different
> > workcenters, we take different jobs as tasks and workcenters as
> > subtasks.

>
> > For each workcenter (subtask), we have relatively stable workers
> > (resources). I already made groups by workcenters for these resources.
> > We don't want to assign specific resources to subtasks, because we
> > don't care who would do the job. Anyone in the group would be ok. So I
> > try to assign groups on subtasks, but many resources are
> > overallocated. Then I try to build a resource pool, and share
> > resources for different subtasks, but it seems it still doesn't work.
> > Many resources are still overallocated. What should I do to make sure
> > the resources are not overallocated for different subtasks? Is that
> > the proper way to use 'share resource'? Or is there a better way to
> > solve the problem or easy for us to schedule?

>
> > Please help.
> > Thanks,
> > Tracey- Hide quoted text -

>
> - Show quoted text -


Hi, Jan,

I put all in one file, and had a try on level resource. It works.
Thanks.

I have another question. If we don't care who would do the job and
just pick one or two persons to do the job at the time, then how
should I assign resources? If assigning the group instead of
individuals, the duration would be much shorter than it actually is.
Is there a easy way to do that? We don't want to specify some
individuals to the job. We hope to assign labor time in the group
instead of individuals. Is that possible? Please help.

Thanks,
Tracey
Reply With Quote
  #4 (permalink)  
Old 08-01-2008, 04:02 PM
Mike Glen
 
Posts: n/a
Re: Resource overallocation problem

Yes, you can call the resource Workers, or Electricians or whatever and in
the Resource Usage view, assign the Max Units to reflect your situation eg:
300% for 3 workers or whatever numbers you have. Then assign that resource
to the tasks and then level. Project will then level assuming you have no
more than the Max Units you set. However, you can't then assign one of them
by name - it's one or the other.

Hope this helps - please let us know how you get on

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials

=============
I have another question. If we don't care who would do the job and
just pick one or two persons to do the job at the time, then how
should I assign resources? If assigning the group instead of
individuals, the duration would be much shorter than it actually is.
Is there a easy way to do that? We don't want to specify some
individuals to the job. We hope to assign labor time in the group
instead of individuals. Is that possible? Please help.

Thanks,
Tracey


Reply With Quote
  #5 (permalink)  
Old 08-05-2008, 10:24 PM
xinxindong2004@gmail.com
 
Posts: n/a
Re: Resource overallocation problem

On Aug 1, 9:02*am, "Mike Glen" <glenATmvps.org> wrote:
> Yes, you can call the resource Workers, or Electricians or whatever and in
> the Resource Usage view, assign the Max Units to reflect your situation eg:
> 300% for 3 workers or whatever numbers you have. *Then assign that resource
> to the tasks and then level. *Project will then level assuming you haveno
> more than the Max Units you set. *However, you can't then assign one ofthem
> by name - it's one or the other.
>
> Hope this helps - please let us know how you get on
>
> Mike Glen
> MS Project MVP
> Seehttp://tinyurl.com/2xbhcfor my free Project Tutorials
>
> =============


Hi, Mike,

I understand what you said. But if some people in the group take
vacation, how it would reflect to the Max units. Do I have to do it
manually? Is there a way I input the exceptional days for different
workers, and Max units for the group would be changed automatically?
Please help.

Thanks,
Tracey
Reply With Quote
  #6 (permalink)  
Old 08-10-2008, 09:30 PM
Mike Glen
 
Posts: n/a
Re: Resource overallocation problem

Hi Tracey,

Sorry for the delay - I've been away. If you wish to allow for holidays,
etc, you will have to manually adjust the avilability contour in the
resource Availability dialog (double-click the resource name on the Resource
Sheet view). When using generic resources in this way, you cannot control
an individual's availability in any other way that I'm aware of.

Mike Glen
Project MVP




xinxindong2004@gmail.com wrote:
> On Aug 1, 9:02 am, "Mike Glen" <glenATmvps.org> wrote:
>> Yes, you can call the resource Workers, or Electricians or whatever
>> and in the Resource Usage view, assign the Max Units to reflect your
>> situation eg: 300% for 3 workers or whatever numbers you have. Then
>> assign that resource to the tasks and then level. Project will then
>> level assuming you have no more than the Max Units you set. However,
>> you can't then assign one of them by name - it's one or the other.
>>
>> Hope this helps - please let us know how you get on
>>
>> Mike Glen
>> MS Project MVP
>> Seehttp://tinyurl.com/2xbhcfor my free Project Tutorials
>>
>> =============

>
> Hi, Mike,
>
> I understand what you said. But if some people in the group take
> vacation, how it would reflect to the Max units. Do I have to do it
> manually? Is there a way I input the exceptional days for different
> workers, and Max units for the group would be changed automatically?
> Please help.
>
> Thanks,
> Tracey



Reply With Quote
  #7 (permalink)  
Old 08-12-2008, 10:47 PM
xinxindong2004@gmail.com
 
Posts: n/a
Re: Resource overallocation problem

On Aug 10, 2:30*pm, "Mike Glen" <glenATmvps.org> wrote:
> Hi Tracey,
>
> Sorry for the delay - I've been away. *If you wish to allow for holidays,
> etc, you will have to manually adjust the avilability contour in the
> resource Availability dialog (double-click the resource name on the Resource
> Sheet view). *When using generic resources in this way, you cannot control
> an individual's availability in any other way that I'm aware of.
>
> Mike Glen
> Project MVP
>
>
>
> xinxindong2...@gmail.com wrote:
> > On Aug 1, 9:02 am, "Mike Glen" <glenATmvps.org> wrote:
> >> Yes, you can call the resource Workers, or Electricians or whatever
> >> and in the Resource Usage view, assign the Max Units to reflect your
> >> situation eg: 300% for 3 workers or whatever numbers you have. Then
> >> assign that resource to the tasks and then level. Project will then
> >> level assuming you have no more than the Max Units you set. However,
> >> you can't then assign one of them by name - it's one or the other.

>
> >> Hope this helps - please let us know how you get on

>
> >> Mike Glen
> >> MS Project MVP
> >> Seehttp://tinyurl.com/2xbhcformy free Project Tutorials

>
> >> =============

>
> > Hi, Mike,

>
> > I understand what you said. But if some people in the group take
> > vacation, how it would reflect to the Max units. Do I have to do it
> > manually? Is there a way I input the exceptional days for different
> > workers, and Max units for the group would be changed automatically?
> > Please help.

>
> > Thanks,
> > Tracey- Hide quoted text -

>
> - Show quoted text -


Hi Mike,

Thanks for your help. If you consider our situation from the
beginning, the repetition job environment, the information for total
labor time in the coming weeks, would you help me to figure out a
better way to make the schedule? I am thinking probably you would have
an efficient way to do this, instead of assigning individuals or max
unit of groups to tasks.

Thanks,
Tracey
Reply With Quote
  #8 (permalink)  
Old 08-13-2008, 09:13 AM
Mike Glen
 
Posts: n/a
Re: Resource overallocation problem

Hi Tracey,

There is a better way and that is to use a program that's designed for
controlling production Project is designed for those once only, unique
undertakings with a clearly defined start and finish. You can't use
individual calendars for a group, but you can use a group calendar, but I
don't believe that will be of use to you. Max units is the only way to go,
and varying the units by time to meet you resource absences is your only
sensible option with Project.

Other than that, I believe you are in danger of micro-managing. Except for
major absences like holidays or longer-term sickness, leave the Max Units
alone. Project is a scheduling program based on the estimated times you
enter. Be more generous with your estimates and let the local management
( foreman?) fit the workers into their slots. If your tasks really are
repetitive, you can then refine your estimates.

Mike Glen
Project MVP





<xinxindong2004@gmail.com> wrote in message
news:32a15468-f8f9-4df5-906a-52bd616eaf6d@p31g2000prf.googlegroups.com...
On Aug 10, 2:30 pm, "Mike Glen" <glenATmvps.org> wrote:
> Hi Tracey,
>
> Sorry for the delay - I've been away. If you wish to allow for holidays,
> etc, you will have to manually adjust the avilability contour in the
> resource Availability dialog (double-click the resource name on the
> Resource
> Sheet view). When using generic resources in this way, you cannot control
> an individual's availability in any other way that I'm aware of.
>
> Mike Glen
> Project MVP
>
>
>
> xinxindong2...@gmail.com wrote:
> > On Aug 1, 9:02 am, "Mike Glen" <glenATmvps.org> wrote:
> >> Yes, you can call the resource Workers, or Electricians or whatever
> >> and in the Resource Usage view, assign the Max Units to reflect your
> >> situation eg: 300% for 3 workers or whatever numbers you have. Then
> >> assign that resource to the tasks and then level. Project will then
> >> level assuming you have no more than the Max Units you set. However,
> >> you can't then assign one of them by name - it's one or the other.

>
> >> Hope this helps - please let us know how you get on

>
> >> Mike Glen
> >> MS Project MVP
> >> Seehttp://tinyurl.com/2xbhcformy free Project Tutorials

>
> >> =============

>
> > Hi, Mike,

>
> > I understand what you said. But if some people in the group take
> > vacation, how it would reflect to the Max units. Do I have to do it
> > manually? Is there a way I input the exceptional days for different
> > workers, and Max units for the group would be changed automatically?
> > Please help.

>
> > Thanks,
> > Tracey- Hide quoted text -

>
> - Show quoted text -


Hi Mike,

Thanks for your help. If you consider our situation from the
beginning, the repetition job environment, the information for total
labor time in the coming weeks, would you help me to figure out a
better way to make the schedule? I am thinking probably you would have
an efficient way to do this, instead of assigning individuals or max
unit of groups to tasks.

Thanks,
Tracey


Reply With Quote
  #9 (permalink)  
Old 08-13-2008, 06:04 PM
xinxindong2004@gmail.com
 
Posts: n/a
Re: Resource overallocation problem

Thanks, Mike.

Just like you said, our schedule is not so strict and I don't have to
make a perfect one. Right now we do everything manually, just want to
use project to save some time for scheduling. Thanks again.

Tracey

On Aug 13, 2:13*am, "Mike Glen" <glenATmvps.org> wrote:
> Hi Tracey,
>
> There is a better way and that is to use a program that's designed for
> controlling production *Project is designed for those once only, unique
> undertakings with a clearly defined start and finish. *You can't use
> individual calendars for a group, but you can use a group calendar, but I
> don't believe that will be of use to you. Max units is the only way to go,
> and varying the units by time to meet you resource absences is your only
> sensible option with Project.
>
> Other than that, I believe you are in danger of micro-managing. *Exceptfor
> major absences like holidays or longer-term sickness, *leave the Max Units
> alone. *Project is a scheduling program based on the estimated times you
> enter. *Be more generous with your estimates and let the local management
> ( foreman?) fit the workers into their slots. *If your tasks really are
> repetitive, you can then refine your estimates.
>
> Mike Glen
> Project MVP
>
> <xinxindong2...@gmail.com> wrote in message
>
> news:32a15468-f8f9-4df5-906a-52bd616eaf6d@p31g2000prf.googlegroups.com...
> On Aug 10, 2:30 pm, "Mike Glen" <glenATmvps.org> wrote:
>
>
>
>
>
> > Hi Tracey,

>
> > Sorry for the delay - I've been away. If you wish to allow for holidays,
> > etc, you will have to manually adjust the avilability contour in the
> > resource Availability dialog (double-click the resource name on the
> > Resource
> > Sheet view). When using generic resources in this way, you cannot control
> > an individual's availability in any other way that I'm aware of.

>
> > Mike Glen
> > Project MVP

>
> > xinxindong2...@gmail.com wrote:
> > > On Aug 1, 9:02 am, "Mike Glen" <glenATmvps.org> wrote:
> > >> Yes, you can call the resource Workers, or Electricians or whatever
> > >> and in the Resource Usage view, assign the Max Units to reflect your
> > >> situation eg: 300% for 3 workers or whatever numbers you have. Then
> > >> assign that resource to the tasks and then level. Project will then
> > >> level assuming you have no more than the Max Units you set. However,
> > >> you can't then assign one of them by name - it's one or the other.

>
> > >> Hope this helps - please let us know how you get on

>
> > >> Mike Glen
> > >> MS Project MVP
> > >> Seehttp://tinyurl.com/2xbhcformyfree Project Tutorials

>
> > >> =============

>
> > > Hi, Mike,

>
> > > I understand what you said. But if some people in the group take
> > > vacation, how it would reflect to the Max units. Do I have to do it
> > > manually? Is there a way I input the exceptional days for different
> > > workers, and Max units for the group would be changed automatically?
> > > Please help.

>
> > > Thanks,
> > > Tracey- Hide quoted text -

>
> > - Show quoted text -

>
> Hi Mike,
>
> Thanks for your help. If you consider our situation from the
> beginning, the repetition job environment, the information for total
> labor time in the coming weeks, would you help me to figure out a
> better way to make the schedule? I am thinking probably you would have
> an efficient way to do this, instead of assigning individuals or max
> unit of groups to tasks.
>
> Thanks,
> Tracey- Hide quoted text -
>
> - Show quoted text -


Reply With Quote
  #10 (permalink)  
Old 08-14-2008, 04:45 PM
Mike Glen
 
Posts: n/a
Re: Resource overallocation problem

You're welcome, Tracey, and good luck :-)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials


<xinxindong2004@gmail.com> wrote in message
news:93fa3558-375b-4e49-bb4a-b5343044aa63@l33g2000pri.googlegroups.com...
Thanks, Mike.

Just like you said, our schedule is not so strict and I don't have to
make a perfect one. Right now we do everything manually, just want to
use project to save some time for scheduling. Thanks again.

Tracey

On Aug 13, 2:13 am, "Mike Glen" <glenATmvps.org> wrote:
> Hi Tracey,
>
> There is a better way and that is to use a program that's designed for
> controlling production Project is designed for those once only, unique
> undertakings with a clearly defined start and finish. You can't use
> individual calendars for a group, but you can use a group calendar, but I
> don't believe that will be of use to you. Max units is the only way to go,
> and varying the units by time to meet you resource absences is your only
> sensible option with Project.
>
> Other than that, I believe you are in danger of micro-managing. Except for
> major absences like holidays or longer-term sickness, leave the Max Units
> alone. Project is a scheduling program based on the estimated times you
> enter. Be more generous with your estimates and let the local management
> ( foreman?) fit the workers into their slots. If your tasks really are
> repetitive, you can then refine your estimates.
>
> Mike Glen
> Project MVP
>
> <xinxindong2...@gmail.com> wrote in message
>
> news:32a15468-f8f9-4df5-906a-52bd616eaf6d@p31g2000prf.googlegroups.com...
> On Aug 10, 2:30 pm, "Mike Glen" <glenATmvps.org> wrote:
>
>
>
>
>
> > Hi Tracey,

>
> > Sorry for the delay - I've been away. If you wish to allow for holidays,
> > etc, you will have to manually adjust the avilability contour in the
> > resource Availability dialog (double-click the resource name on the
> > Resource
> > Sheet view). When using generic resources in this way, you cannot
> > control
> > an individual's availability in any other way that I'm aware of.

>
> > Mike Glen
> > Project MVP

>
> > xinxindong2...@gmail.com wrote:
> > > On Aug 1, 9:02 am, "Mike Glen" <glenATmvps.org> wrote:
> > >> Yes, you can call the resource Workers, or Electricians or whatever
> > >> and in the Resource Usage view, assign the Max Units to reflect your
> > >> situation eg: 300% for 3 workers or whatever numbers you have. Then
> > >> assign that resource to the tasks and then level. Project will then
> > >> level assuming you have no more than the Max Units you set. However,
> > >> you can't then assign one of them by name - it's one or the other.

>
> > >> Hope this helps - please let us know how you get on

>
> > >> Mike Glen
> > >> MS Project MVP
> > >> Seehttp://tinyurl.com/2xbhcformyfree Project Tutorials

>
> > >> =============

>
> > > Hi, Mike,

>
> > > I understand what you said. But if some people in the group take
> > > vacation, how it would reflect to the Max units. Do I have to do it
> > > manually? Is there a way I input the exceptional days for different
> > > workers, and Max units for the group would be changed automatically?
> > > Please help.

>
> > > Thanks,
> > > Tracey- Hide quoted text -

>
> > - Show quoted text -

>
> Hi Mike,
>
> Thanks for your help. If you consider our situation from the
> beginning, the repetition job environment, the information for total
> labor time in the coming weeks, would you help me to figure out a
> better way to make the schedule? I am thinking probably you would have
> an efficient way to do this, instead of assigning individuals or max
> unit of groups to tasks.
>
> Thanks,
> Tracey- Hide quoted text -
>
> - Show quoted text -




Reply With Quote
Reply

  { mindfrost82.com } > Gadget Corner > Tech Newsgroups > Microsoft > MS Office > Project


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On



All times are GMT. The time now is 12:56 AM.


Powered by vBulletin, Copyright ©2000 - 2008, Jelsoft Enterprises Ltd.
Search Engine Friendly URLs by vBSEO 3.1.0 ©2007, Crawlability, Inc.
© 1999-2008 mindfrost82.com v11.0

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109