![]() |
|
|
|||
|
duration and work tracking
I can't seem to figure out how projects tracks things. If I set a project
duration to be 10 days and the work for that project to be 240 hours but the task ends up being put on hold for a few days and starting again, changing the actual duration also changes the actual work. I don't want it to do that. |
|
|||
|
Re: duration and work tracking
Changing actual duration suggests that actual progress was made. If a task
is put on hold then: Update the task to show progress so far If the delay is a number of days, set the timescale to day by day, if weeks then week by week Click and drag (or I prefer to say rip and drag!) the remaining part of the task to when the work will resume. project automatically leaves actual work where it is and only moves remaining work/duration. Actual Duration will remain the same, but the finish date changes and there is a resume date for when the split part restarts. -- Rod Gill Microsoft MVP for Project Author of the only book on Project VBA, see: http://www.projectvbabook.com "monstadunk" <monstadunk@discussions.microsoft.com> wrote in message news:126B182C-170F-4691-8DFD-83E7C198816B@microsoft.com... >I can't seem to figure out how projects tracks things. If I set a project > duration to be 10 days and the work for that project to be 240 hours but > the > task ends up being put on hold for a few days and starting again, changing > the actual duration also changes the actual work. I don't want it to do > that. |
![]() |
|
| Thread Tools | Search this Thread |
| Display Modes | |
|
|