Estimated finish
We work the first time with Project and have some troubles putting one of our
ideas into action. For our project we would like to enter estimated finish times/dates. This would be for tasks which will finish on time (estimated finish = baseline finish), but especially for tasks that we see will be delayed and finish after the baseline finishing date. So far we only found "actual finish", which can only be entered if you have finished the task now (% complete = 100%). But what we're looking for is a possibility to enter a date say three days in the future if we see this task will be finished in three days. The % compoleted could for now also be 60% and only 100% in three days. Is it possible to enter an estimated finish time and then let it show also in the bar diagramm of the GANTT Chart? And in case there were dependencies, could they be recalculated based on the estimated finish date as well? Thanks for any help! Cristina |
|
|||
|
Re: Estimated finish
Hi,
I don't like the idea (Project has to tell me what is the most likely finish) but yes of course, you can - change the estimated duration or - Give the task a finsh no earlier than constraint. Hope this helps, -- Jan De Messemaeker Microsoft Project Most Valuable Professional +32 495 300 620 For availability check: http://users.online.be/prom-ade/Calendar.pdf "Cristina" <Cristina@discussions.microsoft.com> wrote in message news:B9AF1A4D-C1BC-49C1-96E8-86EB407C81D4@microsoft.com... > We work the first time with Project and have some troubles putting one of > our > ideas into action. > For our project we would like to enter estimated finish times/dates. This > would be for tasks which will finish on time (estimated finish = baseline > finish), but especially for tasks that we see will be delayed and finish > after the baseline finishing date. So far we only found "actual finish", > which can only be entered if you have finished the task now (% complete = > 100%). But what we're looking for is a possibility to enter a date say > three > days in the future if we see this task will be finished in three days. The > % > compoleted could for now also be 60% and only 100% in three days. Is it > possible to enter an estimated finish time and then let it show also in > the > bar diagramm of the GANTT Chart? And in case there were dependencies, > could > they be recalculated based on the estimated finish date as well? > > Thanks for any help! > Cristina |
|
|||
|
Re: Estimated finish
On Wed, 23 Jul 2008 05:18:08 -0700, Cristina wrote:
> We work the first time with Project and have some troubles putting one of our > ideas into action. > For our project we would like to enter estimated finish times/dates. This > would be for tasks which will finish on time (estimated finish = baseline > finish), but especially for tasks that we see will be delayed and finish > after the baseline finishing date. So far we only found "actual finish", > which can only be entered if you have finished the task now (% complete = > 100%). But what we're looking for is a possibility to enter a date say three > days in the future if we see this task will be finished in three days. The % > compoleted could for now also be 60% and only 100% in three days. Is it > possible to enter an estimated finish time and then let it show also in the > bar diagramm of the GANTT Chart? And in case there were dependencies, could > they be recalculated based on the estimated finish date as well? > > Thanks for any help! > Cristina If you track properly, you should always be seeing your "estimated" finish. All the start and finish dates in project are estimated until they are replaced with actual dates in the tracking process. If you track by entering Actual Work and Remaining Work, your finish date on that task will be your estimated finish, based on the lastest information. You don't need anything more. What would an additional "estimated" finish do? Hope this helps in your world. |
![]() |
|
| Thread Tools | Search this Thread |
| Display Modes | |
|
|