Welcome to the { mindfrost82.com } forums. You are currently viewing our boards as a guest which gives you limited access to view most discussions and access our other features. By joining our free community you will have access to post topics, communicate privately with other members (PM), respond to polls, upload content and access many other special features. Registration is fast, simple and absolutely free so please, join our community today! If you have any problems with the registration process or your account login, please contact contact us. |
|
|||||||
![]() |
|
|
LinkBack | Thread Tools | Search this Thread | Display Modes |
|
|||
|
expenses MSP 2007
Hi,
I have MSP 2007; how can I enter and track expenses; how can I enter and track expenes for 5 people team, we have 60 dlls for food daily; but at the end of the week I know how much was expensed by every one; how can I get the variance at the end of the week/month? |
|
|||
|
RE: expenses MSP 2007
Unless this relates to specific tasks in a schedule, this calcuation would be
better suited for Excel. We don't normally track travel in Project other than to put down the daily per diem ($60/day) as part of a task. Then it is just a matter of enterring the actuals. From there insert the Cost Variance (CV) column and Project does the work for you (assuming you have a baseline). -- If this post was helpful, please consider rating it. Jim Check out my new blog for more information: http://www.msprojectblog.com "Antonio" wrote: > Hi, > > I have MSP 2007; how can I enter and track expenses; how can I enter and > track expenes for 5 people team, we have 60 dlls for food daily; but at the > end of the week I know how much was expensed by every one; how can I get the > variance at the end of the week/month? > |
![]() |
|
| Thread Tools | Search this Thread |
| Display Modes | |
|
|