Welcome to the { mindfrost82.com } forums. You are currently viewing our boards as a guest which gives you limited access to view most discussions and access our other features. By joining our free community you will have access to post topics, communicate privately with other members (PM), respond to polls, upload content and access many other special features. Registration is fast, simple and absolutely free so please, join our community today! If you have any problems with the registration process or your account login, please contact contact us. |
|
|||||||
![]() |
|
|
LinkBack | Thread Tools | Search this Thread | Display Modes |
|
|||
|
Gantt Bar: is possible to show only the resources that have Remainingwork not equal to "zero"??
hi all,
I'm trying to understand hoe I can view in the Gantt Chart, only the resources that have some work to perform... is there any option to do that?? thank you so much Cheers Vit |
|
|||
|
Re: Gantt Bar: is possible to show only the resources that have Remaining work not equal to "zero"??
Isn't it really the case that you are interested in the Tasks that have not
yet finished? There is a Filter for this. If you find these, then you also have the answer to your question about which Resources still have Work to do. Trevor Rabey 0407213955 61 8 92727485 PERFECT PROJECT PLANNING www.perfectproject.com.au "Vit" <FiNaR76@gmail.com> wrote in message news:b0a403ee-a7f0-42a9-8afb-c515626f9a87@b2g2000prf.googlegroups.com... > hi all, > > I'm trying to understand hoe I can view in the Gantt Chart, only the > resources that have some work to perform... > > is there any option to do that?? > > thank you so much > > Cheers > > Vit |
![]() |
|