Welcome to the { mindfrost82.com } forums. You are currently viewing our boards as a guest which gives you limited access to view most discussions and access our other features. By joining our free community you will have access to post topics, communicate privately with other members (PM), respond to polls, upload content and access many other special features. Registration is fast, simple and absolutely free so please, join our community today! If you have any problems with the registration process or your account login, please contact contact us. |
|
|||||||
![]() |
|
|
LinkBack | Thread Tools | Search this Thread | Display Modes |
|
|||
|
MS Project SchedulingError
Hi, I have Project Schedule have two or three sub-Project in this project, this Project I have left as checked-out befor 15 days but yesterday when again I try to open the project in read view mode..It gives one message window to ask "contains linked information. Do you want to re-establish the links?" I select there to not update links I get the error below(See attached file). after this when I click 'Ok' on this message window then I am not able to see my schedule task, It comes blank sheet, there are not task showing. I am not sure why it is not showing the Tasks. I am choosing the option not update links so Is this the reason no tasks show up in the schedule? Is there a way to open the schedule without it analyzing circular links? Is there a way for MS project to inform a user a circular link is being created before the project is saved? I am not certain it will be recovered. I would really like to understand how I can avoid having the project saved in a state that makes it unrecoverable. Please let me know anyone have any idea Thanks, Rahul +-------------------------------------------------------------------+ |Filename: error.bmp | |Download: http://forums.techarena.in/attachment.php?attachmentid=6494| +-------------------------------------------------------------------+ -- mukulbhind ------------------------------------------------------------------------ mukulbhind's Profile: http://forums.techarena.in/member.php?userid=27489 View this thread: http://forums.techarena.in/showthread.php?t=885478 http://forums.techarena.in |
|
|||
|
Re: MS Project SchedulingError
In article <mukulbhind.32nvbh@DoNotSpam.com>,
mukulbhind <mukulbhind.32nvbh@DoNotSpam.com> wrote: > Hi, > I have Project Schedule have two or three sub-Project in this project, > this Project I have left as checked-out befor 15 days but yesterday > when again I try to open the project in read view mode..It gives one > message window to ask "contains linked information. Do you want to > re-establish the links?" I select there to not update links I get the > error below(See attached file). after this when I click 'Ok' on this > message window then I am not able to see my schedule task, It comes > blank sheet, there are not task showing. I am not sure why it is not > showing the Tasks. > I am choosing the option not update links so Is this the reason no > tasks show up in the schedule? > Is there a way to open the schedule without it analyzing circular > links? > Is there a way for MS project to inform a user a circular link is being > created before the project is saved? > > I am not certain it will be recovered. I would really like to > understand how I can avoid having the project saved in a state that > makes it unrecoverable. Please let me know anyone have any idea > > Thanks, > Rahul > > > +-------------------------------------------------------------------+ > |Filename: error.bmp | > |Download: http://forums.techarena.in/attachment.php?attachmentid=6494| > +-------------------------------------------------------------------+ Rahul, The fact that you are getting a message asking to update links tells me you have used paste links between files. Paste links are fragile and corrupt easily. You would be much better off to link tasks between projects using external predecessors/successors. With regard to circular relationships. Aside from the fragility of paste links, the single most prevalent reason for circular relationships is when a user puts links on summary lines. This is compounded when working with a master project with inserted subprojects. However, this may or may not be relevant in your case since you didn't mention any error messages warning about circular relationships. John Project MVP |
|
|||
|
Re: MS Project SchedulingError
In article <mukulbhind.32nvbh@DoNotSpam.com>,
mukulbhind <mukulbhind.32nvbh@DoNotSpam.com> wrote: > Hi, > I have Project Schedule have two or three sub-Project in this project, > this Project I have left as checked-out befor 15 days but yesterday > when again I try to open the project in read view mode..It gives one > message window to ask "contains linked information. Do you want to > re-establish the links?" I select there to not update links I get the > error below(See attached file). after this when I click 'Ok' on this > message window then I am not able to see my schedule task, It comes > blank sheet, there are not task showing. I am not sure why it is not > showing the Tasks. > I am choosing the option not update links so Is this the reason no > tasks show up in the schedule? > Is there a way to open the schedule without it analyzing circular > links? > Is there a way for MS project to inform a user a circular link is being > created before the project is saved? > > I am not certain it will be recovered. I would really like to > understand how I can avoid having the project saved in a state that > makes it unrecoverable. Please let me know anyone have any idea > > Thanks, > Rahul > > > +-------------------------------------------------------------------+ > |Filename: error.bmp | > |Download: http://forums.techarena.in/attachment.php?attachmentid=6494| > +-------------------------------------------------------------------+ Rahul, The fact that you are getting a message asking to update links tells me you have used paste links between files. Paste links are fragile and corrupt easily. You would be much better off to link tasks between projects using external predecessors/successors. With regard to circular relationships. Aside from the fragility of paste links, the single most prevalent reason for circular relationships is when a user puts links on summary lines. This is compounded when working with a master project with inserted subprojects. However, this may or may not be relevant in your case since you didn't mention any error messages warning about circular relationships. John Project MVP |
|
|||
|
Re: MS Project SchedulingError
Hi John, Thanks for your response. As I have mention in previous mail that when I am open this project in Read View mode(because Project is Checked-out), I am not able to see my Project schedule there are no Task showing in MSP Sheet, so Please tell me how can I retrieve my project to see and then after further I can do breaks the links and other activities, but first should be able to see my project, because when open this project there comes first message window(See attached file1) and then when I click on 'No' again another message window comes(see attached file2) and when click ok then it come blank sheet. Please help me to retrieved project so that I can see all the tasks. Thanks, Rahul +-------------------------------------------------------------------+ |Filename: ErrorMessage2.bmp | |Download: http://forums.techarena.in/attachment.php?attachmentid=6497| +-------------------------------------------------------------------+ -- mukulbhind ------------------------------------------------------------------------ mukulbhind's Profile: http://forums.techarena.in/member.php?userid=27489 View this thread: http://forums.techarena.in/showthread.php?t=885478 http://forums.techarena.in |
|
|||
|
Re: MS Project SchedulingError
Hi John, Thanks for your response. As I have mention in previous mail that when I am open this project in Read View mode(because Project is Checked-out), I am not able to see my Project schedule there are no Task showing in MSP Sheet, so Please tell me how can I retrieve my project to see and then after further I can do breaks the links and other activities, but first should be able to see my project, because when open this project there comes first message window(See attached file1) and then when I click on 'No' again another message window comes(see attached file2) and when click ok then it come blank sheet. Please help me to retrieved project so that I can see all the tasks. Thanks, Rahul +-------------------------------------------------------------------+ |Filename: ErrorMessage2.bmp | |Download: http://forums.techarena.in/attachment.php?attachmentid=6497| +-------------------------------------------------------------------+ -- mukulbhind ------------------------------------------------------------------------ mukulbhind's Profile: http://forums.techarena.in/member.php?userid=27489 View this thread: http://forums.techarena.in/showthread.php?t=885478 http://forums.techarena.in |
|
|||
|
Re: MS Project SchedulingError
In article <mukulbhind.32t1ff@DoNotSpam.com>,
mukulbhind <mukulbhind.32t1ff@DoNotSpam.com> wrote: > Hi John, > > Thanks for your response. As I have mention in previous mail that when > I am open this project in Read View mode(because Project is > Checked-out), I am not able to see my Project schedule there are no > Task showing in MSP Sheet, so Please tell me how can I retrieve my > project to see and then after further I can do breaks the links and > other activities, but first should be able to see my project, because > when open this project there comes first message window(See attached > file1) and then when I click on 'No' again another message window > comes(see attached file2) and when click ok then it come blank sheet. > Please help me to retrieved project so that I can see all the tasks. > > Thanks, > Rahul > > > +-------------------------------------------------------------------+ > |Filename: ErrorMessage2.bmp | > |Download: http://forums.techarena.in/attachment.php?attachmentid=6497| > +-------------------------------------------------------------------+ Rahul, You must be working with Project Server. Sorry, I can't help you with that. I suggest you post to our sister newsgroup, microsoft.public.project.server. This newsgroup is dedicated to questions/issues with the stand alone version of Project. John Project MVP |
|
|||
|
Re: MS Project SchedulingError
In article <mukulbhind.32t1ff@DoNotSpam.com>,
mukulbhind <mukulbhind.32t1ff@DoNotSpam.com> wrote: > Hi John, > > Thanks for your response. As I have mention in previous mail that when > I am open this project in Read View mode(because Project is > Checked-out), I am not able to see my Project schedule there are no > Task showing in MSP Sheet, so Please tell me how can I retrieve my > project to see and then after further I can do breaks the links and > other activities, but first should be able to see my project, because > when open this project there comes first message window(See attached > file1) and then when I click on 'No' again another message window > comes(see attached file2) and when click ok then it come blank sheet. > Please help me to retrieved project so that I can see all the tasks. > > Thanks, > Rahul > > > +-------------------------------------------------------------------+ > |Filename: ErrorMessage2.bmp | > |Download: http://forums.techarena.in/attachment.php?attachmentid=6497| > +-------------------------------------------------------------------+ Rahul, You must be working with Project Server. Sorry, I can't help you with that. I suggest you post to our sister newsgroup, microsoft.public.project.server. This newsgroup is dedicated to questions/issues with the stand alone version of Project. John Project MVP |
![]() |
|